The Ho Chi Minh City - Long Thanh Expressway expansion project is nearly 22km long, with an investment of more than VND 15,337 billion, expected to start construction on August 19, 2025 and strive to be completed in 2026.
The Government Office has just issued Document No. 6166/VPCP-CN conveying the direction of Deputy Prime Minister Tran Hong Ha on implementing the project to expand the Ho Chi Minh City-Long Thanh Expressway section under the emergency construction project.
Specifically, in Document No. 5889/VPCP-CN dated June 26, 2025 of the Government Office, Deputy Prime Minister Tran Hong Ha agreed with the proposal of the Ministry of Finance and Vietnam Expressway Corporation (VEC) on implementing the Project according to the procedures for urgent projects.
The Deputy Prime Minister requested the Ministry of Finance and VEC to take full responsibility for the content of the report and commitment; organize the implementation of the Project to ensure progress, quality, safety, and to avoid loopholes, corruption, group interests, causing loss and damage to state assets.
The Ho Chi Minh City-Long Thanh Expressway Expansion Project has a total investment scope of nearly 22km. The starting point of the project is at Km 4+000 (Ring Road 2 Intersection) in Thu Duc City, Ho Chi Minh City. The end point is at Km 25+920 (Bien Hoa-Vung Tau Expressway Intersection) in Long Thanh District, Dong Nai Province.
In terms of scale, the Ring Road 2-Ring Road 3 viaduct section (Km 4+000-Km 8+44.5) will be expanded by 7.75m on each side to reach a scale of 8 lanes. Of which, the total width of the bridge is 42m including 2 units. The section from Ring Road 3 to the Bien Hoa-Vung Tau expressway interchange (Km 8+44.5-Km 25+920) will be invested in expanding to a scale of 10 lanes.
The total preliminary investment of the project is about more than 15,337 billion VND. Of which, compensation, support and resettlement costs are more than 967 billion VND; construction costs are more than 11,116 billion VND; equipment costs are nearly 99 billion VND; project management, consulting and other costs are more than 1,126 billion VND; contingency costs are more than 1,980 billion VND.
The project is expected to start construction on August 19, 2025 and be basically completed in 2026./.
Source: https://baolangson.vn/cao-toc-thanh-pho-ho-chi-minh-long-thanh-thuc-day-hoan-thanh-vao-nam-2026-5052504.html