Forces of Phu Xuan Ward People's Committee organized to dismantle the roof and assets affecting the project.

The Van Xuan Bridge project has 5 households affected by the site; of which, 2 households will be resettled, 3 households will only have their property affected. Currently, the Project Management Board of the Hue City Type II Urban Development Program continues to work with the Vietnam Railway Authority to soon relocate the railway crossing.

Mr. Le Thanh Bac, Deputy Director of the Project Management Board of the Program for Development of Type II Urban Areas of Hue City, said that immediately after receiving the direction of the City People's Committee, the unit coordinated with the locality to mobilize people and organize the dismantling of assets affecting the project.

Van Xuan Bridge is nearly 40m long, with a 6.5m wide bridge deck connecting Pham Thi Lien Street to Le Duan Street (Hue City). Van Xuan Bridge has completed 2 abutments, 1 pillar, 2 bridge spans and poured concrete for 2 bridge decks. As for the road leading to the bridge, the contractor is currently constructing and the project is expected to be completed before September 2.

Van Xuan Bridge strives to be completed before September 2

Previously, Van Xuan bridge was a temporary bridge, made of iron, small and narrow. The traffic volume of people and vehicles passing through this bridge was very high, leading to overload, causing traffic pressure. To facilitate traffic as well as help this area become more spacious, in addition to dredging and building embankments along Ke Van river, the functional sector demolished the old bridge to build the new Van Xuan bridge.

Regarding this bridge, previously, Hue Today Newspaper also had an article mentioning the concerns and inadequacies in the site clearance work and what people want is the early completion of Van Xuan bridge.

News and photos: PHONG ANH