Van Ninh - Cam Lo Expressway is one of 12 component projects of the North-South Expressway, Eastern Phase II, 2021 - 2025, 65.54 km long, with a total investment of more than VND 9,919 billion, started construction on January 1, 2023, and is completing the final items to ensure the target of reaching the finish line on August 19, 2025 set by the Government and the Ministry of Construction.

Báo Tin TứcBáo Tin Tức07/07/2025

In early July 2025, reporters from Tin Tuc and Dan Toc newspaper were present at the construction site of the Van Ninh - Cam Lo expressway, recording the urgent atmosphere of hundreds of engineers, supervisory consultants, workers, and laborers of the investor and contractors "overcoming the sun and rain", working in 3 shifts, 4 shifts day and night, stretching across the entire route to serve the goal of reaching the project's finish line.

Video recorded by reporters at the project construction site in early July 2025:

According to Mr. Luu Tuan Tuan, in charge of project construction management (representative of the Ho Chi Minh Road Project Management Board - Investor), by early July 2025, the project had achieved an overall progress of about 97.5% of the construction and installation volume. Currently, on the expressway, there are only about 8.5km of service roads that have not been handed over because the locality has not approved the compensation plan; creating the National Highway (QL) 9C intersection with a U-turn point and toll station; on the main route, there are about 170m of the completion stage of the items... but this does not affect the project's target progress.

Photo caption

The entrance to the Van Ninh - Cam Lo highway is as beautiful as a silk strip passing through Quang Tri province.

Photo caption

The main route of Van Ninh - Cam Lo expressway has completed the final layer of asphalt concrete.

Photo caption

Contractor workers construct a soft median strip on the highway.

Photo caption

Contractor workers anchor the slope and prevent landslides with B40 steel mesh.

Photo caption

The contractor must both construct and ensure traffic safety on the route.

According to the reporter's records, the Van Ninh - Cam Lo expressway is divided into 2 construction packages: XL1 from Km675+400 - Km708+350, with 13 bridges, 108 box culverts, 17 underpasses; XL2 from Km708+350 - Km740+884, with 16 bridges, 129 box culverts, 25 underpasses. Currently, the 2 packages have basically completed the main construction items such as: Final layer of hot asphalt concrete, road marking paint, installation of lighting system, guardrail fences, intelligent traffic management...

“Contractors on the route are organizing many construction teams along the entire route to complete the installation of warning signs, road guidance gates, anti-slide anchors, soft median strips on the highway, turn-around points and toll stations… If the weather conditions are favorable, with the current accelerated progress, the project will reach the target set by the Government and the Ministry of Construction,” said Mr. Luu Tuan Tuan.

Photo caption

The Van Ninh - Cam Lo expressway section has completed all items and is waiting for the opening day.

Photo caption

Workers complete the installation of traffic signs on the highway.

Photo caption

The project still has some problems with the site related to the residential road, the turning point, the toll station on the route... but they do not affect the overall progress.

Photo caption

The expressway overpass projects on the route are expected to be completed in July 2025.

Photo caption

The starting point of Van Ninh - Cam Lo expressway connecting with Bung - Van Ninh expressway is also being urgently completed.

Photo caption

Contractors paved the last meters of asphalt concrete on the highway.

At the end of June 2025, during the inspection of the expressway site, to ensure the progress of the main route opening and completion of the project in July 2025, Deputy Minister of Construction Nguyen Tuong Van requested the Ho Chi Minh Road Project Management Board to continue to closely monitor the site, proactively and actively work with the locality to complete site clearance for frontage roads, rest stops, and toll stations; In case of difficulties, report to the People's Committee of Quang Tri province and the Ministry of Construction, prioritizing site clearance locations related to the main route opening.

Photo caption

The highway passing through An Ma Lake is considered the most beautiful route on the project route.

Photo caption

The contractor is speeding up the completion of An Ma Bridge, the longest bridge on the highway.

Photo caption

The final meters of the highway are being completed in sync with the finishing line.

Photo caption

Highway location waiting for toll station installation on the route.

 

Photo caption

The contractor must level the mountain, strengthen and anchor the positive slope system with steel mesh to prevent landslides.

Photo caption

Currently, project contractors are focusing on completing the overpass system, residential roads and road markings...

Photo caption

The Van Ninh - Cam Lo highway runs parallel to Ho Chi Minh road.

The Van Ninh - Cam Lo Expressway starts at the Bung - Van Ninh Expressway in Quang Binh Province (old) and ends at the Cam Lo - La Son Expressway in Quang Tri Province (old). When completed and put into operation, the expressway will shorten travel time, creating momentum to promote trade, socio-economic development, and tourism in the new Quang Tri Province and the localities where the project passes through.

According to the Ministry of Construction's plan, on August 19, 2025, 6 North-South expressway component projects will open to traffic on the main route or some sections on the main route, with a total length of 208 km, including: Vung Ang - Bung, Van Ninh - Cam Lo, the remaining 13 km of Van Phong - Nha Trang expressway, some sections of Quang Ngai - Hoai Nhon expressway (10/88 km), Hoai Nhon - Quy Nhon (45/70 km), Quy Nhon - Chi Thanh (20/62 km) and the Hoa Lien - Tuy Loan expressway. The remaining projects are being implemented with efforts, basically following the completion plan by the end of 2025.

Tien Hieu-Trung Nguyen/Tin Tuc and Dan Toc Newspaper

Source: https://baotintuc.vn/anh/cao-toc-van-ninh-cam-lo-tang-toc-can-dich-dung-muc-tieu-chinh-phu-de-ra-20250706093522730.htm


Comment (0)

No data
No data

Same tag

Same category

How is the most expensive tea in Hanoi, priced at over 10 million VND/kg, processed?
Taste of the river region
Beautiful sunrise over the seas of Vietnam
The majestic cave arc in Tu Lan

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product