Reporting to the Standing Vice Chairman of the Ho Chi Minh City People's Committee, the investor's representative said that the project has nearly 30 items, which have been urgently and simultaneously constructed in the past time, thanks to which, so far, all of them have exceeded the set schedule. Most of the construction, finishing, electromechanical and landscape infrastructure work is in the final stage.

There are currently over 500 workers working in 3 shifts, 4 shifts, and many times working through the night. Among the items under construction, the square area has many complex details that require high technology, so the units are concentrating their forces to complete the project on schedule. The goal is to complete the entire project before August 15 to serve the people and tourists during the great festival.
After examining each item and detail of the project, Permanent Vice Chairman of the Ho Chi Minh City People's Committee Nguyen Van Tho requested to edit some details to ensure aesthetic, cultural, historical, coverage and tree species. The leader of the Ho Chi Minh City People's Committee emphasized that the Thuy Van Street project has important significance, with the expectation of building a modern, vibrant and classy open space in Ho Chi Minh City as well as the whole country.
The Standing Vice Chairman of the Ho Chi Minh City People's Committee encouraged and acknowledged the efforts of the investor, contractors and workers at the construction site. In the final stage, relevant agencies and units need to continue to resolutely and meticulously complete the key items down to the smallest details. The project must be completed with all technical and aesthetic factors and ensure the set progress.
Source: https://www.sggp.org.vn/lanh-dao-ubnd-tphcm-thi-sat-du-an-chinh-trang-truc-duong-thuy-van-post803504.html
Comment (0)