Land acquisition issue, bridge worth over 274 billion VND in Da Nang 'froze'

After the technical opening, Quang Da bridge - a project with an investment capital of more than 274 billion VND in Da Nang city - fell into a "frozen" situation due to land clearance problems.

VTC NewsVTC News09/07/2025

Land acquisition issue, over 274 billion VND bridge in Da Nang 'froze' - 1

Quang Da Bridge crosses the Yen River, connecting Hoa Tien Commune with Dien Ban Bac Commune ( Da Nang City). The project started construction in December 2023, with a total investment of more than 274 billion VND.

Land acquisition issues, over 274 billion VND bridge in Da Nang 'froze' - 2

The project is a level II traffic project, with the investment policy decided by the Da Nang People's Council; the Da Nang Traffic and Agricultural Construction Investment Project Management Board is the investor, project manager, and supervision consultant. The construction period according to the contract is from December 2023 to May 2025.

Land acquisition issue, over 274 billion VND bridge in Da Nang 'froze' - 3

The Quang Da Bridge and approach road project has a total length of over 1.4km, with a scale of 4 lanes. Of which, the bridge is 204m long and 22m wide; the approach road at both ends of the bridge is over 1.2km long with the starting point of the route intersecting with National Highway 14B at Km31+087.

Land acquisition issues, bridge worth over 274 billion VND in Da Nang 'froze' - 4

At the end of March 2025, the People's Committee of Da Nang City held a ceremony to technically open the Quang Da Bridge and the approach road. However, after the technical opening, this project with an investment capital of more than 274 billion VND still cannot be put into operation due to site clearance problems.

Land acquisition issues, over 274 billion VND bridge in Da Nang 'froze' - 5

According to records, the road leading to the bridge on the Hoa Tien commune side has been completed, connecting directly to National Highway 14B. The contractor is completing additional items such as positive slope, planting trees, and creating surrounding landscape.

Land acquisition issue, bridge worth over 274 billion VND in Da Nang 'froze' - 6

As for Dien Ban Bac commune, the construction progress of the Northern Quang Nam beltway connecting to Quang Da bridge is still sluggish. The road leading to the bridge has not been able to be constructed yet.

Land acquisition issues, over 274 billion VND bridge in Da Nang 'froze' - 7

The contractor put up a dead-end sign from Hoa Tien commune and erected a barrier to restrict people from crossing the bridge.

Land acquisition issues, bridge worth over 274 billion VND in Da Nang 'froze' - 8

Ms. Nguyen Thi Minh Chau - Chairman of Dien Ban Bac Commune People's Committee - said that the delay in the project's construction was related to site clearance. Previously, the project was invested by Dien Ban Town (old), after the establishment of the new administrative unit, the commune is taking over the remaining work.

Source: https://vtcnews.vn/vuong-mat-bang-cau-hon-274-ty-dong-o-da-nang-dung-hinh-ar953367.html


Comment (0)

No data
No data
Mysterious cave attracts Western tourists, likened to 'Phong Nha cave' in Thanh Hoa
Discover the poetic beauty of Vinh Hy Bay
How is the most expensive tea in Hanoi, priced at over 10 million VND/kg, processed?
Taste of the river region
Beautiful sunrise over the seas of Vietnam
The majestic cave arc in Tu Lan
Lotus tea - A fragrant gift from Hanoi people
More than 18,000 pagodas nationwide rang bells and drums to pray for national peace and prosperity this morning.
The Han River sky is 'absolutely cinematic'
Miss Vietnam 2024 named Ha Truc Linh, a girl from Phu Yen

Heritage

Figure

Business

No videos available

News

Political System

Local

Product