Member of the Party Central Committee, Minister of Construction Tran Hong Minh inspected the construction progress of the Long Thanh Airport Project Phase 1 on July 11. Photo: Pham Tung |
This is one of four projects under Component Project 4 assigned by the Government to the Provincial People's Committee to select investors.
Total investment of nearly 1.5 trillion VND
At the end of March 2025, Deputy Prime Minister Tran Hong Ha signed a decision approving the adjustment of the Long Thanh Airport Project Phase 1. In this decision, one of the adjusted contents is that the Government assigned the Provincial People's Committee to organize the selection of investors for the following projects: fuel pipeline system for aircraft from the upstream port to the boundary of Long Thanh Airport; airport city; aviation industrial park and airline operations center.
According to the Department of Construction, the Aircraft Fuel Pipeline Project at Long Thanh Airport has a scale of investment in the construction of 2 parallel pipelines, each line is more than 23km long, with an expected pipe diameter of 12-16 inches connecting from the source warehouse at Go Dau Industrial Park to the storage warehouse of Long Thanh Airport.
“The total estimated investment of the project is nearly 1.5 trillion VND, including costs for site clearance, construction, equipment, project management…” - Deputy Director of the Department of Construction Duong Van Hieu said.
The Department of Construction proposed that the Provincial People's Committee direct the Department of Finance to allocate additional funding for the hiring of a consulting unit for the Project of Fuel Pipeline for Aircraft at Long Thanh Airport. The estimated cost is about 300 million VND from the province's public fund. |
As the unit assigned by the Provincial People's Committee to advise and propose to the Provincial People's Committee to select investors for the project, the Department of Construction has just proposed to the Provincial People's Committee to approve the hiring of a consulting unit to select investors in special cases for the Aircraft Fuel Pipeline Project at Long Thanh Airport, including the following steps: preparing a request file and evaluating the proposal file, appraising the request file and the results of contractor selection.
Explaining the proposal to hire a consulting unit to implement, Mr. Duong Van Hieu said that Clause 4, Article 78 of the Bidding Law No. 22/2023/QH15 stipulates that the preparation of a request for bid evaluation and appraisal of request documents, appraisal of contractor and investor selection results must be carried out by self-implementation or hiring a qualified organization to do so. In addition, according to Clause 1, Article 19 of Decree 24/2024/ND-CP, which stipulates the conditions for capacity and experience of expert teams and appraisal teams, members must have a professional certificate in bidding and have at least 3 years of work experience in one of the fields related to the legal, technical and financial contents of the bidding package.
Construction of Long Thanh Airport Project Phase 1. |
However, the experts of the Department of Construction do not meet the requirements on capacity and experience as prescribed above because they are not in the management field according to the functions and tasks. "Therefore, with the urgent progress to complete the selection of investors in July 2025, the Department of Construction proposes to the Provincial People's Committee to approve the bidding party, the Department of Construction, to hire a consulting unit to carry out the selection of investors in special cases for this project" - Mr. Duong Van Hieu added.
Priority implementation
In addition to proposing a form of investor selection, the Department of Construction recommended that the Provincial People's Committee direct localities, including Phuoc Thai and Long Thanh communes, to update relevant planning to implement the project.
Regarding land allocation and leasing to implement the Aircraft Fuel Pipeline Project at Long Thanh Airport, Deputy Director of the Department of Agriculture and Environment Tran Trong Toan proposed the form of land lease with annual payment instead of land lease with one-time payment to shorten the project implementation time.
The Long Thanh Airport Construction Investment Project Phase 1 is a special national key project. According to the Prime Minister's request, the project must be basically completed by the end of 2025 and put into commercial operation in the first half of 2026. This requires that the project items, including the aircraft fuel pipeline system, must be completed synchronously within the above time period.
Faced with urgent requirements for implementation progress, Vice Chairman of the Provincial People's Committee Ho Van Ha requested the Department of Construction to prioritize the selection of project investors. Localities and functional agencies should focus on reviewing and completing legal documents for planning related to project investment implementation.
According to the Department of Construction, regarding the implementation progress, the Aircraft Fuel Pipeline Project at Long Thanh Airport will be implemented in 2025 and 2026, of which it must be basically completed in 2025.
Pham Tung