Vietnam.vn - Nền tảng quảng bá Việt Nam

More than 10,800 billion VND of public investment capital for Ho Chi Minh City's traffic needs to be disbursed.

TPO - Although it has entered the second half of the year, the Ho Chi Minh City Department of Transport has only disbursed 37% of the public investment capital plan for 2025. The remaining VND 10,800 billion (accounting for 63% of the plan) needs to be disbursed from now until the end of the year, equivalent to about VND 1,800 billion/month.

Báo Tiền PhongBáo Tiền Phong11/07/2025

"Bottleneck" of materials and premises

In 2025, the Ho Chi Minh City Traffic Construction Investment Project Management Board (Traffic Board) was assigned by the City People's Committee a public investment plan of more than VND 17,271 billion to implement a series of key infrastructure projects. However, according to the latest report, by early July, this unit had only disbursed about VND 6,403 billion, equivalent to 37% of the assigned plan.

Thus, in just the remaining 6 months, the Traffic Department must disburse more than 10,868 billion VND, equivalent to more than 1,800 billion VND per month.

More than 10,800 billion VND of public investment capital for Ho Chi Minh City's traffic needs to be disbursed photo 1

An Phu Interchange - a key project at the eastern gateway of Ho Chi Minh City is behind schedule. Photo: Duy Anh

Mr. Luong Minh Phuc - Director of the Ho Chi Minh City Transport Department said that the rate of public investment disbursement in the first half of this year was low because many projects were in the process of completing legal procedures, could not organize bidding and sign construction contracts, so they were not eligible to disburse advance capital to contractors.

“In addition, the scarcity of construction materials, especially sand, has caused difficulties in the construction process, slowed down progress and reduced the volume of work. In addition, site clearance in some localities is still slow, causing many projects to not be implemented as planned, directly affecting the progress of capital disbursement,” a representative of the Ho Chi Minh City Transport Department analyzed.

Shorten the time to carry out investment procedures

Faced with the pressure to disburse all allocated capital in 2025, the Ho Chi Minh City Transport Department has proposed a series of solutions to "sprint".

According to Mr. Luong Minh Phuc - Director of Ho Chi Minh City Department, the unit has built a detailed schedule for each project each month and each quarter, focusing on urging and directing the construction unit to increase the construction teams of "3 shifts, 4 teams" to speed up the construction progress, to ensure the disbursement progress reaches 100% in 2025.

Notably, this unit also recommended that the City People's Committee direct departments, branches and localities to shorten at least 30% of the time to carry out investment procedures, especially BOT projects to expand gateways, such as: the project to upgrade and expand National Highway 1, the project to renovate and expand National Highway 22, the North-South axis road (from Nguyen Van Linh to Ben Luc - Long Thanh expressway) and the upgrade and expansion of National Highway 13.

“The goal is to disburse the huge amount of compensation capital for site clearance of these projects,” said Mr. Phuc.

More than 10,800 billion VND of public investment capital for Ho Chi Minh City's traffic needs to be disbursed photo 2

Currently, the Ho Chi Minh City Transport Department is speeding up the progress of the Ring Road 3 project.

In addition, the Traffic Department is urgently promoting new projects to start construction in order to sign contracts soon and disburse the advance payment according to regulations. The disbursement working groups are also assigned the responsibility of regularly checking, urging, and promptly reporting any problems so that the city can quickly handle them.

In order for the capital flow of more than 10,800 billion VND for transportation to "flow smoothly" from now until the end of the year, the prerequisite is to have drastic and synchronous participation from many sides, from local authorities to specialized departments.

According to experts, timely disbursement not only helps Ho Chi Minh City avoid the risk of capital transfer but also plays an important role in stimulating investment, creating jobs and promoting economic growth.

"We clearly define our responsibilities and are focusing all our efforts to ensure that the disbursement reaches 100% of the capital plan this year," Mr. Luong Minh Phuc affirmed.

Source: https://tienphong.vn/hon-10800-ty-dong-von-dau-tu-cong-cho-giao-thong-tphcm-can-phai-giai-ngan-post1759121.tpo


Comment (0)

No data
No data
Image of terraced fields in Phu Tho, gently sloping, bright and beautiful like mirrors before the planting season
Z121 Factory is ready for the International Fireworks Final Night
Famous travel magazine praises Son Doong cave as 'the most magnificent on the planet'
Mysterious cave attracts Western tourists, likened to 'Phong Nha cave' in Thanh Hoa
Discover the poetic beauty of Vinh Hy Bay
How is the most expensive tea in Hanoi, priced at over 10 million VND/kg, processed?
Taste of the river region
Beautiful sunrise over the seas of Vietnam
The majestic cave arc in Tu Lan
Lotus tea - A fragrant gift from Hanoi people

Heritage

Figure

Business

No videos available

News

Political System

Local

Product