Early relocation of technical infrastructure, speeding up the progress of Van Phong expressway

Báo Giao thôngBáo Giao thông15/08/2024


Speed up technical infrastructure relocation, early handover of rest stop site

Deputy Minister Nguyen Duy Lam led a working delegation of the Ministry of Transport to directly inspect the entire Van Phong - Nha Trang expressway in Khanh Hoa province, with a length of more than 80km.

At the Co Ma tunnel intersection, the leader of the People's Committee of Van Ninh district ( Khanh Hoa ) said that the work of relocating power lines and solar power systems is being urgently implemented. However, there are still some locations that have not been completed.

Sớm di dời hạ tầng kỹ thuật, đẩy nhanh tiến độ cao tốc Vân Phong - Nha Trang- Ảnh 1.

Deputy Minister Nguyen Duy Lam (second from right) listens to a report on the implementation of the Van Phong - Nha Trang expressway.

Proposing that localities speed up the relocation progress and complete it in August 2024, Deputy Minister Nguyen Duy Lam noted that units need to proactively coordinate with the electricity sector and flexibly arrange power outage schedules to avoid affecting the project's construction progress.

Regarding the existence of some solar power transformer station locations affecting the project site, the Deputy Minister suggested that Khanh Hoa province continue to work with the investor and relevant levels to find a solution.

Sớm di dời hạ tầng kỹ thuật, đẩy nhanh tiến độ cao tốc Vân Phong - Nha Trang- Ảnh 2.

A working delegation from the Ministry of Transport inspected the construction site at Km367, Van Phong - Nha Trang expressway.

Regarding the progress of construction of the rest stop on the Van Phong - Nha Trang highway, the Deputy Minister requested the People's Committee of Khanh Hoa province to direct departments and branches to focus on supporting Ninh Hoa town to develop and complete the site clearance plan, and promptly build the station on schedule.

"If the rest stop site is handed over on schedule (before September 30), it will help ensure completion at the same time as the project.

Rest stops put into operation in sync with the highway project not only create a place for people to rest and recharge their energy, refuel vehicles after a long journey, but also contribute to ensuring traffic safety, economic development, and become a highlight of the local landscape," the Deputy Minister emphasized.

Strive to basically complete the project by April 30, 2025

Reporting to the Deputy Minister, Mr. Tran Dinh Tuyen, Deputy Director of Project Management Board 7 (investor) said that both construction packages of the Van Phong - Nha Trang expressway project are being simultaneously implemented.

The contractors mobilized a total of 30 construction teams (21 road teams, 9 bridge teams) to the construction site with nearly 1,400 workers and nearly 800 construction equipment of various types.

Sớm di dời hạ tầng kỹ thuật, đẩy nhanh tiến độ cao tốc Vân Phong - Nha Trang- Ảnh 3.

Dozens of kilometers of Van Phong - Nha Trang highway have been paved.

Actual output exceeded the plan by 0.2%. This year's disbursed capital for the project has also reached more than 53% of the assigned capital plan.

According to Project Management Board 7, the overall progress of the entire project has basically met the set plan. Contractors have made great efforts in implementing the construction work, closely following the adjusted construction schedule, with the goal of basically completing it before April 30, 2025.

Sớm di dời hạ tầng kỹ thuật, đẩy nhanh tiến độ cao tốc Vân Phong - Nha Trang- Ảnh 4.

The investor and contractors are determined to complete the project on April 30, 2025.

"Currently, there are still many essential technical infrastructure locations on the route that affect the construction progress, so we request the People's Committee of Ninh Hoa town and Van Ninh district to focus on directing units to relocate 110kV and 220kV high-voltage power projects, prioritizing key locations, and strive to complete before August 30," Mr. Tuyen suggested.

The Van Phong - Nha Trang expressway component project through Khanh Hoa is more than 83km long (passing through 4 districts and towns: Van Ninh, Ninh Hoa, Dien Khanh and Khanh Vinh).

The project has a total investment of more than 11,000 billion VND, and will start construction in January 2023.



Source: https://www.baogiaothong.vn/som-di-doi-ha-tang-ky-thuat-day-tien-do-cao-toc-van-phong-nha-trang-19224081422540203.htm

Comment (0)

No data
No data
Magical scene on the 'upside down bowl' tea hill in Phu Tho
3 islands in the Central region are likened to Maldives, attracting tourists in the summer
Watch the sparkling Quy Nhon coastal city of Gia Lai at night
Image of terraced fields in Phu Tho, gently sloping, bright and beautiful like mirrors before the planting season
Z121 Factory is ready for the International Fireworks Final Night
Famous travel magazine praises Son Doong cave as 'the most magnificent on the planet'
Mysterious cave attracts Western tourists, likened to 'Phong Nha cave' in Thanh Hoa
Discover the poetic beauty of Vinh Hy Bay
How is the most expensive tea in Hanoi, priced at over 10 million VND/kg, processed?
Taste of the river region

Heritage

Figure

Business

No videos available

News

Political System

Local

Product