Also attending were representatives of the departments: Construction, Agriculture and Environment, City People's Committee Office, West Hai Phong Construction Investment Project Management Board, Railway Project Management Board ( Ministry of Construction ), and leaders of localities where the route passes through.
During the field inspection and working session with localities in the western part of the city, Permanent Vice Chairman of the City People's Committee Le Anh Quan acknowledged the proactiveness and determination of localities in implementing tasks related to the Lao Cai - Hanoi - Hai Phong railway project.
.jpg)
However, at present, some implementation work is still slow related to resettlement in Yet Kieu and Gia Loc communes. Through actual inspection, there is still a situation of people illegally building on land within the project scope.
He requested localities to strengthen discipline, tighten land management and construction order, and strictly handle violations according to the law. At the same time, step up propaganda so that people understand that violations will not be entitled to compensation and support policies. Resolutely stop illegal construction activities, and prevent the recurrence of encroachment on project land.

The Standing Vice Chairman of Hai Phong City People's Committee requested localities to focus on implementing the work of measuring, extracting, and determining the origin of land; proactively developing implementation plans when there is an official route.
The Standing Vice Chairman of the City People's Committee assigned the West Hai Phong Construction Investment Project Management Board to closely coordinate with localities in identifying and implementing resettlement areas. Regularly update and provide information on design, route direction, and related policies to coordinate with localities in site clearance work.

At the same time, the Department of Agriculture and Environment and the Department of Construction are assigned to coordinate in guiding and supporting localities in implementing compensation and resettlement support policies; appraising and approving plans according to regulations.
Emphasizing that the railway project is a national key project, the Standing Vice Chairman of the City People's Committee requested the authorities of communes and functional branches to focus highly, considering this a key political task, and to be determined to ensure the progress and effectiveness of project implementation.
.jpg)
On the same afternoon, Mr. Le Anh Quan, Standing Vice Chairman of the City People's Committee, inspected the Public Administration Service Centers of Gia Phuc and Yet Kieu communes. He highly appreciated the preparation of facilities at the centers; at the same time, requested to continue to maintain the spirit of serving the people attentively, not to let delays or inconveniences occur in handling administrative procedures. Localities stabilized the organization, maintained good operations and effectively carried out assigned political tasks.
The investment project to build the Lao Cai - Hanoi - Hai Phong railway line through Hai Phong city has a total length of about 89.88 km (40.96 km in the western part of the city, 48.92 km in the eastern part of the city); passing through 24 communes, wards and special zones, including: Cam Giang, Ke Sat, Mao Dien, Binh Giang, Yet Kieu, Gia Loc, Gia Phuc, Tan Ky, Tu Ky, Dai Son, Chi Minh, Ha Dong, An Quang, Quyet Thang, An Khanh, An Hung, Kien Thuy, Kien Minh, Duong Kinh, Hai An, Dong Hai, Nam Do Son, Kien Hai, Cat Hai special zone.
The total land acquisition area is about 624.13 hectares, the total number of affected households is 6,096 households, the total cost of site clearance is about 9,753 billion VND.
Source: https://baohaiphongplus.vn/vice-chairman-of-hai-phong-city-ubnd-le-anh-quan-kiem-tra-thuc-dia-du-an-duong-sat-lao-cai-ha-noi-hai-phong-415930.html