With a determined and urgent spirit, Hai Phong City is speeding up the work groups under its responsibility in implementing the Lao Cai - Hanoi - Hai Phong Railway Construction Investment Project.
The city has assigned the task of implementing 14 resettlement projects including 11 projects in the old Hai Duong and 3 projects in the old Hai Phong with 9 resettlement areas. The total area for implementing the resettlement projects is about 59.86 hectares. The estimated cost is about 1,237 billion VND.
The Lao Cai – Hanoi – Hai Phong railway construction investment project through Hai Phong city has a total length of about 89.88 km, passing through 24 communes, wards and special zones. The project reclaims about 624.13 hectares of land from 6,096 households, with a cost of about 9,753 billion VND for site clearance. Of which, 1,749 households need to be resettled (407 households in the old Hai Duong, 1,342 households in the old Hai Phong).
According to plan, the resettlement project will start in July 2025 and be completed in November 2025.
The Lao Cai – Hanoi – Hai Phong railway project is a national key project, of strategic significance in forming a railway transport network in the north, strengthening inter-regional connectivity, and promoting socio-economic development of the localities through which the route passes.
HNSource: https://baohaiphongplus.vn/hai-phong-trien-khai-14-du-an-tai-dinh-cu-phuc-vu-du-an-duong-sat-lao-cai-ha-noi-hai-phong-416050.html
Comment (0)