Vietnam.vn - Nền tảng quảng bá Việt Nam

Lao Cai - Vinh Yen 500kV Transmission Line Project: Completing the first cable pulls

(Chinhphu.vn) - Power Project Management Board 1 and the contractor have just completed pulling the first anchors from location VT9 to VT16 of the 500kV Lao Cai - Vinh Yen transmission line project.

Báo Chính PhủBáo Chính Phủ04/07/2025

Dự án Đường dây 500kV Lào Cai - Vĩnh Yên: Hoàn thành kéo dây những khoảng néo đầu tiên- Ảnh 1.

A pole position of the 500kV Lao Cai - Vinh Yen Transmission Line project

VT9 - VT16 positions belong to package HH1 implemented by the joint venture of Song Da Construction and Service Joint Stock Company - PC1 Group Joint Stock Company - Dong Anh Steel Column Manufacturing Company Limited. Package 1 of the project includes 51 column positions, from VT1 to VT52, passing through Lao Cai province.

Mr. Do Quang Khai, Deputy Director of Power Project Management Board 1, said that the completion of the first wire pulling sections is an important milestone, and at the same time creates strong motivation and encouragement for other teams, groups and contractors working on the construction site, aiming to ensure the progress of the project's wire pulling work.

To achieve this result, the Power Project Management Board 1 and the contractor had to face and overcome many challenges. In fact, during the implementation of work at locations VT9 - VT16, there were times when people did not agree to transport equipment and materials through residential roads. At the same time, the construction terrain was complicated, the pole locations in this wire pulling area were all located on high hills. In addition, the weather was unfavorable, the project area had been experiencing prolonged rain for nearly a week, greatly affecting the work of constructing foundations, erecting poles and spreading and pulling wires along the entire route.

Faced with these difficulties, the Power Project Management Board 1 has implemented many synchronous solutions. In terms of management and supervision of the construction site, the Power Project Management Board 1 has arranged specialized departments to be on duty at pole locations to promptly coordinate with local authorities and contractors to resolve any problems and difficulties arising during the wire pulling process. In the site clearance work, the Power Project Management Board 1 has closely coordinated with local authorities to mobilize people to support the project construction, agreeing to cut down trees in the route corridor to speed up progress.

The Power Project Management Board 1 also assigned qualified staff to be on duty at the construction site regularly to guide contractors, promptly resolve problems and accept the work to quickly move on to the next step of construction. At the same time, it directed contractors to take advantage of the time when it is not raining to speed up construction implementation.

On the contractor's side, Mr. Nguyen Cao Ngoc, Deputy General Director of Song Da Construction and Service Joint Stock Company, said that the unit has applied modern technology, using flycams to spread bait lines in the air and a brake machine, helping to shorten the time to spread and pull the lines, avoiding having to lower the lines many times, causing waste of time and prolonging the progress.

Previously, Package No. 1 was also the first package to complete all foundation pit work in the Lao Cai - Vinh Yen 500kV Transmission Line project. With the determination to join hands with the investor, the contractor of Package No. 1 said that it would be ready to support and "share the burden" with other construction units to carry out the work on the construction site, aiming for the ultimate goal of energizing the project on August 19, 2025 as directed by the Prime Minister .

Vu Phong


Source: https://baochinhphu.vn/du-an-duong-day-500kv-lao-cai-vinh-yen-hoan-thanh-keo-day-nhung-khoang-neo-dau-tien-102250704102129761.htm


Comment (0)

No data
No data
Z121 Factory is ready for the International Fireworks Final Night
Famous travel magazine praises Son Doong cave as 'the most magnificent on the planet'
Mysterious cave attracts Western tourists, likened to 'Phong Nha cave' in Thanh Hoa
Discover the poetic beauty of Vinh Hy Bay
How is the most expensive tea in Hanoi, priced at over 10 million VND/kg, processed?
Taste of the river region
Beautiful sunrise over the seas of Vietnam
The majestic cave arc in Tu Lan
Lotus tea - A fragrant gift from Hanoi people
More than 18,000 pagodas nationwide rang bells and drums to pray for national peace and prosperity this morning.

Heritage

Figure

Business

No videos available

News

Political System

Local

Product