The company will build the North-South axis road from National Highway 5 (km 65 + 700) through Kim Thanh Industrial Park to the residential area of Bo Ho village, Vu Dung commune, now Lai Vu commune ( Hai Phong city). The total length of the route is about 2 km.
The route has a width of 60 m including: main road surface, 11 m on each side, 9 m/side service road, in addition to median strip, sidewalk, drainage system, traffic safety, trees, lighting... The project uses nearly 12 hectares of land in Lai Vu commune.
The total investment of the project is nearly 348 billion VND, all of which are legal capital sources of Coma 18 Joint Stock Company.
The project is divided into 2 phases. Phase 1 (2025 - 2026) will carry out site clearance and investment in the section from National Highway 5 to the end of Kim Thanh Industrial Park, with a total length of about 1,028km; invest in building a main road with a width of 24m; intersection with National Highway 5...
Phase 2 (2027 - 2028), clear the remaining section and invest in completing the entire planned route with a width of 60 m; build intersections, drainage systems, traffic safety, trees, and lighting according to regulations.
The implementation of the North-South axis road project through Kim Thanh Industrial Park will connect the traffic infrastructure in the industrial park with National Highway 5 and other routes, facilitating travel and transport of goods in and out of the industrial park; ensuring safety for people and vehicles participating in traffic; creating conditions for local socio -economic development.
Coma 18 Joint Stock Company is also the investor of Kim Thanh Industrial Park.
PVSource: https://baohaiphongplus.vn/cong-ty-cp-coma-18-dau-tu-gan-348-ty-dong-xay-dung-duong-truc-bac-nam-qua-khu-cong-nghiep-kim-thanh-416015.html