With an initial capacity of 50MW, this is the first time the power plant has been connected to the grid, marking an important milestone in the testing process before commercial operation. Previously, on June 6, Nhon Trach 4 Power Plant successfully conducted the first ignition and ran in idle mode at 3,000 rpm, an important technical step for putting the turbine into loaded testing operation.
The operation of Nhon Trach 4 Thermal Power Plant is of great significance as in recent years, no large power plant has been put into operation, causing the risk of power shortage in the near future.
Source: https://quangngaitv.vn/nhiet-dien-nhon-trach-4-chinh-thuc-hoa-luoi-dien-quoc-gia-6504265.html