The working group inspected the progress of house construction in Ban Cu Nha La.
It is known that this time, Doan Ket ward has 59 houses that have started construction and repair. Through inspection, many houses have completed 70 - 90% of the construction volume, some houses are ready to be handed over for use. Taking advantage of favorable weather, units and households are speeding up the construction progress.
Comrade Tong Thanh Binh - Member of the Provincial Party Standing Committee, Secretary of the Ward Party Committee visited and encouraged families who received support to remove temporary and dilapidated houses.
Currently, there are 4 houses whose construction progress is behind schedule, due to prolonged rain, leading to difficulties in transporting materials, affecting progress.
Through the actual inspection, Comrade Tong Thanh Binh - Member of the Provincial Party Standing Committee, Secretary of the Ward Party Committee directed specialized agencies to coordinate with the Provincial Military Command to quickly accelerate the progress of eliminating temporary and dilapidated houses; Party cells to help the village with a plan to support working days; strengthen inspection and supervision of disbursement for households to build houses...
Source: https://baolaichau.vn/xa-hoi/kiem-tra-tien-do-xoa-nha-tam-nha-dot-nat-1310094
Comment (0)