According to Mr. Thi, the overall progress of the Rach Mieu 2 Bridge Construction Investment Project has reached over 96.5%. Of which, the road and approach road to Rach Mieu 2 Bridge have been basically completed, the construction unit is completing the installation of median strips, road markings, lighting, etc., which will be completed before July 20.

The main cable-stayed bridge has completed the casting of the guardrail, installation of the guardrail, median strip and expansion joints, and is currently implementing the asphalt concrete pavement of the bridge deck.

After that, we will continue to complete the bridge's auxiliary items, cable-stayed/damping vibration measurement experiments, and implement bridge load testing... According to My Thuan Project Management Board, the entire Rach Mieu 2 Bridge Project will be completed by early August 2025.

Currently, at the construction site, there are nearly 600 workers and technical staff from the units continuing to maintain the construction "3 shifts, 4 teams" with 30 construction teams and 150 construction equipment. All are determined to complete the project as directed by the Prime Minister .

The Rach Mieu 2 Bridge Project starts at Dong Tam intersection (the intersection between National Highway 1 and Provincial Road 870) in Dong Thap province; the project ends at about Km16+660 National Highway 60, about 0.71km from the northern abutment of Ham Luong Bridge, in Vinh Long province. The project has a total investment of more than 6,810 billion VND, with My Thuan Project Management Board as the investor.

Rach Mieu 2 main bridge is a cable-stayed bridge, with a length of 1,971.2m, a 4-lane level III delta road, the total length of the project is about 17.6km. When completed, the project will help reduce pressure on the existing Rach Mieu bridge, minimizing traffic congestion on weekends and holidays.

Source: https://www.sggp.org.vn/hoan-thanh-du-an-cau-rach-mieu-2-vao-dau-thang-8-2025-post802783.html