Rach Mieu 2 Bridge Project to be completed in early August 2025

On July 7, Mr. Tran Van Thi, Director of My Thuan Project Management Board, said that the Rach Mieu 2 Bridge Construction Investment Project (connecting Dong Thap and Vinh Long provinces) has so far completed all 6/6 bridges on the route including: the main cable-stayed bridge, Xoai Hot bridge, My Tho bridge, Tam Son bridge, Ba Lai bridge and Song Ma bridge.

Báo Sài Gòn Giải phóngBáo Sài Gòn Giải phóng07/07/2025

z6780105233069_4b77c784d90796245b1c91528ea90132.jpg
Overall, the Rach Mieu 2 Bridge Construction Investment Project has reached more than 96.5%.

According to Mr. Thi, the overall progress of the Rach Mieu 2 Bridge Construction Investment Project has reached over 96.5%. Of which, the road and approach road to Rach Mieu 2 Bridge have been basically completed, the construction unit is completing the installation of median strips, road markings, lighting, etc., which will be completed before July 20.

z6780105211744_9f358549e940524b445241aebcb0021c.jpg
The main cable-stayed bridge is preparing to deploy asphalt concrete paving work.

The main cable-stayed bridge has completed the casting of the guardrail, installation of the guardrail, median strip and expansion joints, and is currently implementing the asphalt concrete pavement of the bridge deck.

z6780105225305_3510bfc789295101051049cfc0fd28fe.jpg
Asphalt concrete pavement

After that, we will continue to complete the bridge's auxiliary items, cable-stayed/damping vibration measurement experiments, and implement bridge load testing... According to My Thuan Project Management Board, the entire Rach Mieu 2 Bridge Project will be completed by early August 2025.

z6780105205811_7f0795806a6b278fa0136790cf9e1a2b.jpg
The construction unit is completing the installation of lighting.

Currently, at the construction site, there are nearly 600 workers and technical staff from the units continuing to maintain the construction "3 shifts, 4 teams" with 30 construction teams and 150 construction equipment. All are determined to complete the project as directed by the Prime Minister .

z6780105155268_3f64bd1bd9d0cb6710dd189a90446ae9.jpg
The construction unit is installing the railing.

The Rach Mieu 2 Bridge Project starts at Dong Tam intersection (the intersection between National Highway 1 and Provincial Road 870) in Dong Thap province; the project ends at about Km16+660 National Highway 60, about 0.71km from the northern abutment of Ham Luong Bridge, in Vinh Long province. The project has a total investment of more than 6,810 billion VND, with My Thuan Project Management Board as the investor.

z6780105174694_924b5bd2a0986f130e6a95125e1f4074.jpg
The construction unit is completing the installation of median strips and road markings.

Rach Mieu 2 main bridge is a cable-stayed bridge, with a length of 1,971.2m, a 4-lane level III delta road, the total length of the project is about 17.6km. When completed, the project will help reduce pressure on the existing Rach Mieu bridge, minimizing traffic congestion on weekends and holidays.

z6780105167560_8044e67b025caeaa62e7247624b63a82.jpg

Source: https://www.sggp.org.vn/hoan-thanh-du-an-cau-rach-mieu-2-vao-dau-thang-8-2025-post802783.html


Comment (0)

No data
No data

Same tag

Same category

How is the most expensive tea in Hanoi, priced at over 10 million VND/kg, processed?
Taste of the river region
Beautiful sunrise over the seas of Vietnam
The majestic cave arc in Tu Lan

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product