Accordingly, the Underpass Project at Co Linh Intersection, Long Bien District will be implemented from 2024 - 2026. The investment in the project will close the Ring Road 2 according to the planning, while at the same time building a reasonable traffic infrastructure system to resolve traffic conflicts at the intersection, connecting the surrounding roads; gradually completing the traffic infrastructure system and environmental pollution of Hanoi City.
The project has a total investment of 747,593 billion VND using the city budget, with the Hanoi City Traffic Construction Investment Project Management Board as the investor and the inviting party. This is a group B project, with a total of 18 bidding packages, and an implementation period of 2 years.
Package 01/XL Construction of tunnel (including equipment, technical infrastructure works, auxiliary works and synchronous traffic organization) with a price of 599,885 billion VND was issued by the investor and the inviting party to invite bids on June 9, 2025, expected to open bids at 5:00 p.m. on June 27, 2025.
The implementation period of the bid package is 26 months, the bid package is widely bid online, the method of selecting contractors is one stage, one envelope.
Source: https://baophapluat.vn/ha-noi-dau-thau-goi-thau-xay-dung-ham-chui-tai-nut-giao-co-linh-long-bien-gan-600-ty-dong-post551913.html
Comment (0)