The Project to invest in the construction of Ring Road 3 - Ho Chi Minh City section through the province (Component Project 3) is over 11km long, starting at the intersection with Ben Luc - Long Thanh Expressway, ending at pier B of Nhon Trach Bridge. The project has a total investment of nearly 2.6 trillion VND. By the end of 2024, the project has disbursed 770 billion VND, reaching 100% of the capital plan.
Regarding the progress of construction packages, the project is implementing 3 main construction packages with a cumulative value of 760 billion VND, reaching 41% of the signed contract value, about 4.7% behind schedule.
Of the three main construction packages of the project, package 29, which constructs the section from the intersection of provincial road 25C to the intersection of provincial road 25B, is the package with the highest implementation value, reaching nearly 50% of the signed contract value. Package 32, which constructs the section from the intersection of provincial road 25B to the end of the route, has an implementation value of more than 38% of the signed contract value, and package 26, which constructs the section from the beginning of the route to the intersection of provincial road 25C, has an implementation value of more than 32% of the signed contract value.
Pham Tung
Source: https://baodongnai.com.vn/kinh-te/202507/giai-ngan-gan-236-ty-dong-von-bo-tri-cho-du-an-duong-vanh-dai-3-thanh-pho-ho-chi-minh-c102ee5/
Comment (0)