Terminal T3 of Tan Son Nhat Airport is 83% completed, operational on April 30, 2025

Báo Đầu tưBáo Đầu tư28/12/2024

The T3 terminal project at Tan Son Nhat Airport has completed more than 83% of the work and is in the process of completing the interior to put into operation on April 30, 2025.


Terminal T3 of Tan Son Nhat Airport is 83% completed, operational on April 30, 2025

The T3 terminal project at Tan Son Nhat Airport has completed more than 83% of the work and is in the process of completing the interior to put into operation on April 30, 2025.

On the afternoon of December 27, Vietnam Airports Corporation (ACV) launched a 120-day and night competition to complete the T3 passenger terminal project at Tan Son Nhat Airport.

Panoramic view of Tan Son Nhat Airport Terminal 3 from above

According to ACV's report, as of December 27, the total volume of the Project has reached more than 83% and the expanded aircraft parking area has been put into operation.

Currently, the contractor is installing the electrical system, air conditioning and ventilation system, fire prevention and fighting system, etc. According to the plan of Vietnam Airports Corporation, the entire project will be completed on April 30, 2025 (2 months ahead of schedule).

The rough part of the station has been completed, now contractors are installing the interior and finishing the exterior decoration.

To shorten the progress, the investor and contractor have applied many synchronous solutions to overcome difficulties in narrow construction sites, rainy weather and especially construction under conditions where Tan Son Nhat Airport is still operating normally.

Most contractors have responded to the Government 's call, working overtime, creating solutions to protect against rain and sun, applying advanced construction technologies, not succumbing to weather difficulties, in keeping with the spirit of overcoming the sun and rain.

The 2-storey overpass system in front of the station has completed the rough construction and is installing railings.

The project to build passenger terminal T3, Tan Son Nhat International Airport includes 4 main items: passenger terminal, multi-storey car park combined with non-aviation services, overpass system in front of the terminal and aircraft parking. The project has a total investment of 10,990 billion VND.

Once completed, the terminal will serve domestic flights with a capacity of 20 million passengers/year, meeting 7,000 passengers/peak hour. At that time, it will solve the congestion at Tan Son Nhat International Airport.



Source: https://baodautu.vn/nha-ga-t3-san-bay-tan-son-nhat-da-hoan-thanh-83-khai-thac-dip-3042025-d236282.html

Comment (0)

No data
No data
PIECES of HUE - Pieces of Hue
Magical scene on the 'upside down bowl' tea hill in Phu Tho
3 islands in the Central region are likened to Maldives, attracting tourists in the summer
Watch the sparkling Quy Nhon coastal city of Gia Lai at night
Image of terraced fields in Phu Tho, gently sloping, bright and beautiful like mirrors before the planting season
Z121 Factory is ready for the International Fireworks Final Night
Famous travel magazine praises Son Doong cave as 'the most magnificent on the planet'
Mysterious cave attracts Western tourists, likened to 'Phong Nha cave' in Thanh Hoa
Discover the poetic beauty of Vinh Hy Bay
How is the most expensive tea in Hanoi, priced at over 10 million VND/kg, processed?

Heritage

Figure

Business

No videos available

News

Political System

Local

Product