Speeding up the progress of Hung Vuong Ecological Park Project

This afternoon, August 18, Vice Chairman of Lam Dong Provincial People's Committee Nguyen Minh chaired a working session with departments, branches and localities to listen to reports on the construction progress of the Hung Vuong Park Project (a flooded ecological park in Phu Thuy ward).

Báo Lâm ĐồngBáo Lâm Đồng18/08/2025

1(8).jpg
Mr. Phan Duc Thanh, representative of Construction Investment Project Management Board No. 2, reported on the progress of Hung Vuong Park Project.

Representative of the Construction Investment Project Management Board No. 2, Mr. Phan Duc Thanh, reported a summary of the project implementation. Accordingly, the project with a scale of 30.08 hectares will invest in the construction of the following items: Observatory, square, outdoor stage; camping area, rest hut; planting trees on water surface, construction of high and low roads; reinforcement of canal embankments; construction of boat docks.

Hung Vuong Park project combines the park perimeter with the riverside promenade, expanding Ton That Tung and Le Dai Hanh streets in the area to serve visitors.

The total investment of the project is 498 billion VND. Currently, the Construction Investment Project Management Board No. 2 has implemented the investment preparation phase such as approving the design, estimate, contractor selection plan, etc.

Meanwhile, recently, the compensation and site clearance work for the Hung Vuong Park Project was carried out by the Binh Thuan Land Fund Development Center (formerly) at the Hung Vuong Residential Area Phase II project, area 4 + 5 in the new Phu Thuy ward, with a total area of over 43 hectares, and a total of 124 households receiving compensation.

To date, there have been decisions on compensation and support for 109 files, covering an area of over 33 hectares. The remaining files are being negotiated for compensation and site clearance by the Lam Dong Provincial Land Fund Development Center after the merger.

At the meeting, functional departments and branches expressed their opinions and requested the Management Board of Construction Investment Project No. 2 and the Land Fund Development Center of Lam Dong province to remove obstacles and speed up the project's construction progress.

Vice President Minh 1
Vice Chairman of Lam Dong Provincial People's Committee Nguyen Minh spoke at the meeting.

After listening to opinions from units, Vice Chairman of Lam Dong Provincial People's Committee Nguyen Minh said that the implementation of work in the past time was still slow.

In the coming time, relevant units need to promptly implement assigned tasks to speed up project implementation progress.

Vice Chairman of Lam Dong Provincial People's Committee Nguyen Minh

The Vice Chairman of the Provincial People's Committee requested the Management Board of Construction Investment Project No. 2 to coordinate with functional units to base on specific urban planning to re-determine and adjust the detailed planning of the project; ensure connection with the surrounding natural landscape, create harmony, and ensure environmental sanitation.

img_6334(1).jpg
Working scene

The Department of Construction is responsible for appraising the project design. Along with that, the Department of Finance advises the Provincial People's Committee to arrange funds to pay for planning costs for the consulting unit.

The Department of Agriculture and Environment reviewed and handed over the compensation and site clearance dossiers to the Lam Dong Provincial Land Fund Development Center so that the center could coordinate with Phu Thuy Ward to carry out propaganda and mobilize people in compensation and site clearance for the remaining dossiers, and support resettlement for households in the project area.

The locality does not allow encroachment or re-encroachment in the project area...

Source: https://baolamdong.vn/day-nhanh-tien-do-du-an-cong-vien-sinh-thai-hung-vuong-387790.html


Comment (0)

No data
No data
People flock to Hanoi, immersing themselves in the heroic atmosphere before National Day.
Suggested locations to watch the parade on National Day September 2
Visit Nha Xa silk village
See beautiful photos taken by flycam by photographer Hoang Le Giang
When young people tell patriotic stories through fashion
More than 8,800 volunteers in the capital are ready to contribute to the A80 festival.
The moment the SU-30MK2 "cuts the wind", air gathers on the back of the wings like white clouds
'Vietnam - Proudly Stepping Forward to the Future' Spreads National Pride
Young people hunt for hair clips and gold star stickers for National Day holiday
See the world's most modern tank, suicide UAV at the parade training complex

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product