Vietnam.vn - Nền tảng quảng bá Việt Nam

Three North-South Expressway projects will open to traffic in August

According to the Ministry of Construction, three sections of the North-South expressway, including Vung Ang - Bung, Van Ninh - Cam Lo and Hoa Lien - Tuy Loan, are expected to open to traffic on August 19.

Báo Hải PhòngBáo Hải Phòng08/07/2025

Bung - Van Ninh Expressway through Quang Binh in April 2025. Photo: Vo Thanh
Bung - Van Ninh Expressway through Quang Binh in April 2025. Photo: VO THANH

Mr. Le Quyet Tien, Director of the Department of Economics and Construction Investment Management, said that this year, about 889 km of 17 projects invested by the Ministry of Construction will be completed.

Among the 12 component projects of the North-South Expressway Phase 2 (2021-2025), the Bai Vot - Ham Nghi, Ham Nghi - Vung Ang, Bung - Van Ninh sections and 70 km of the Van Phong - Nha Trang route have been put into operation since April 30.

By August 19, an additional 208 km of highway will be completed, including the 55 km Vung Ang - Bung section; the 65 km Van Ninh - Cam Lo section; and the 11 km Hoa Lien - Tuy Loan section through Da Nang City, coinciding with Ho Chi Minh Road.

The remaining 13 km of the Van Phong - Nha Trang section was also completed, along with some partially opened sections such as Quang Ngai - Hoai Nhon (10/88 km), Hoai Nhon - Quy Nhon (45/70 km), Quy Nhon - Chi Thanh (20/62 km).

The Ministry of Construction aims to complete all remaining North-South Expressway component projects by December this year.

At the conference on implementing tasks for the last 6 months of 2025 on July 7, Minister of Construction Tran Hong Minh assessed that the progress of public investment disbursement has not yet met expectations. The remaining undisbursed volume is about 63,000 billion VND, with an average of 9,000 billion VND needed to be disbursed each month.

Specialized units are assigned to closely monitor construction progress, especially projects starting or completing this year, towards celebrating the 80th anniversary of National Day, September 2.

The Minister also requested project management boards to urgently complete the selection of contractors to construct the traffic management and monitoring system on the North-South Expressway, ensuring synchronous operation from January 1, 2026.

VN (according to VnExpress)

Source: https://baohaiphongplus.vn/ba-du-an-cao-toc-bac-nam-se-thong-xe-trong-thang-8-415861.html


Comment (0)

No data
No data

Same category

How is the most expensive tea in Hanoi, priced at over 10 million VND/kg, processed?
Taste of the river region
Beautiful sunrise over the seas of Vietnam
The majestic cave arc in Tu Lan

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product