Construction of Cay bridge reaches 30% of volume

Việt NamViệt Nam21/04/2024

image(1).png
Beam casting construction at Cay bridge construction investment project. Photo: THANH CHUNG

The unit mobilized about 50 workers and more than a dozen machines and equipment, divided into construction teams for the river items and casting Super-T beams.

Cay Bridge connects Cam Dong commune (Cam Giang) and Hung Thang commune (Binh Giang). The project is invested by the Provincial Construction Investment Project Management Board.

The scale of the construction project is a level II plain road. The design speed is 80km/h. The bridge is permanently built with prestressed reinforced concrete, the bridge width is 30m, divided into 2 separate bridge units. The total length of the bridge is 182m with 4 spans of Super-T girders.

The construction contractor is the Hai Duong Irrigation Joint Venture - Licogi 18 - Bao Long. The construction supervision contractor is Thang Long Construction Quality Supervision Consulting Joint Stock Company.

The project will be implemented from March 20, 2024, with a construction period of 390 days.

The investor requested the People's Committee of Binh Giang district to urgently complete site clearance and resettlement arrangements for households subject to resettlement... to ensure project construction progress.

HN

Source

Comment (0)

No data
No data

Same tag

Same category

Close-up of the 'steel monsters' showing off their power at A80
Summary of A80 training: Vietnam's strength shines under the night of the thousand-year-old capital
Hanoi traffic chaos after heavy rain, drivers abandon cars on flooded roads
Impressive moments of the flight formation on duty at the A80 Ceremony

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product