Minister of Construction Tran Hong Minh discussed with provincial leaders and relevant units at the construction site of Long Thanh Airport Project. Photo: Pham Tung |
At the Bien Hoa - Vung Tau Expressway Project, the inspection team surveyed the actual construction progress at Tan Hiep intersection and intersections with roads connecting to Long Thanh Airport.
Reporting to the working group, Mr. Nguyen Van Long, Deputy Director of Project Management Board 85, said that for Component Project 2, Bien Hoa - Vung Tau Expressway Project, contractors have completed about 65% of the roadbed embankment output. However, since mid-May, due to heavy rain, the roadbed embankment construction has encountered many difficulties.
Regarding stone materials, contractors have gathered about 40% of the stone needed for construction work at the construction site. To ensure the goal of opening the main route to traffic before December 19, contractors are focusing on working in "3 shifts, 4 shifts", making the most of the time with favorable weather conditions to speed up construction progress.
Minister of Construction Tran Hong Minh gives a speech at the construction site of Tan Hiep intersection, Bien Hoa - Vung Tau Expressway Project. Photo: Pham Tung |
Meanwhile, at Component Project 1, Bien Hoa - Vung Tau Expressway Project, Mr. Nguyen Linh, Deputy Director of the Provincial Construction Investment Project Management Board, said that the project is implementing 2 main packages. Of which, package 18 has achieved output of more than 22% compared to the signed contract; package 21, construction output has reached nearly 50% of the signed contract value. The Provincial Construction Investment Project Management Board also committed to completing the technical traffic of the main route of the project before December 19, of which package 21 is likely to finish first.
At the inspection, Vice Chairman of the Provincial People's Committee Ho Van Ha said that up to now, Dong Nai has basically resolved the problems regarding land and material sources for the construction of the Bien Hoa - Vung Tau Expressway Project. Therefore, contractors need to make efforts and speed up the construction progress to complete the project as required by the Prime Minister.
Minister of Construction Tran Hong Minh gave instructions while inspecting the construction progress at the intersection of Bien Hoa - Vung Tau Expressway with traffic routes connecting Long Thanh Airport. Photo: Pham Tung |
Speaking at the project site, Minister of Construction Tran Hong Minh emphasized that the consistent goal is to complete the technical opening of the entire main route of the Bien Hoa - Vung Tau expressway, the section passing through Dong Nai province, before December 19.
Currently, when the site clearance work and construction materials have basically met the demand, contractors must increase the construction work to "3 shifts, 4 shifts", "working day and night". In particular, according to Minister Tran Hong Minh, in rainy weather conditions, investors must direct contractors to increase manpower and machinery to take advantage of sunny weather to speed up construction progress.
Minister of Construction Tran Hong Minh presents gifts to encourage the construction force of Long Thanh Airport Project. Photo: Pham Tung |
After inspecting the Bien Hoa - Vung Tau Expressway Project, the working group of the Ministry of Construction inspected the actual construction progress of the Long Thanh Airport Project.
Also during the inspection, Minister Tran Hong Minh gave gifts and encouraged the construction force of the projects.