Vice Chairman of the Provincial People's Committee Duong Minh Dung inspected the site clearance work of 3 power projects.

(DN) - On June 11, Member of the Provincial Party Standing Committee, Vice Chairman of the Provincial People's Committee Duong Minh Dung inspected the field and worked with Long Thanh district, Nhon Trach district, and the Southern Power Project Management Board regarding the problems of the high-voltage power project to relieve the capacity of Nhon Trach 3 and Nhon Trach 4 Power Plants.

Báo Đồng NaiBáo Đồng Nai11/06/2025

Vice Chairman of the Provincial People's Committee Duong Minh Dung speaks at the working session with the Long Thanh District People's Committee. Photo: Hoang Loc

According to the report of the Department of Industry and Trade, related to the capacity clearance of the above two power plants, there are 3 power projects still stuck with land clearance.

Specifically, the 220kV line of Nhon Trach 3 Power Plant - Long Thanh 500kV Transformer Station has 87 pole positions, and up to now, 53 poles have been mobilized for handover (51 poles in Nhon Trach district and 2 poles in Long Thanh district).

The 500kV Nhon Trach 4 Power Plant - Phu My - Nha Be branch line has completed the project but there has not been a decision on the compensation plan to pay the households. The 220kV Nhon Trach 3 Power Plant - My Xuan - Cat Lai branch line has mobilized the handover of 11/11 pillars, of which 7 pillars have been erected, the rest are under construction.

Leaders of the Provincial People's Committee, departments, branches, localities and investors inspected the location of the pillar foundation that is still stuck in the ground clearance in Phuoc Khanh commune, Nhon Trach district. Photo: Hoang Loc

Mr. Bui Quang Thanh, Deputy Director of the Southern Power Project Management Board, proposed that the provincial leaders direct the People's Committees of Nhon Trach and Long Thanh districts to speed up the site clearance and compensation work, ensuring the progress of projects to transmit the capacity of Nhon Trach 3 and Nhon Trach 4 power plants to the national power system as required by the Government , while at the same time effectively promoting the investment capital of high-voltage power projects being implemented in the province.

Vice Chairman of the Provincial People's Committee Duong Minh Dung assessed that the two power plants mentioned above have great significance for the national power grid and the economic development and investment environment of the province.

The provincial leaders requested the People's Committee of Nhon Trach district to urgently coordinate with the Southern Power Project Management Board to continue to mobilize the handover of the construction site of the 220kV transmission line of Nhon Trach 3 Power Plant - Long Thanh 500kV Transformer Station to complete the mobilization of the handover of the remaining 32 pillar foundation locations before June 15, 2025 according to the direction of Deputy Prime Minister Bui Thanh Son at the 5th Meeting on May 29, 2025. Implement the price listing and publicize the collection of opinions in parallel with the mobilization of the handover of the construction site of the 220kV transmission line of Nhon Trach 3 Power Plant - Long Thanh 500kV Transformer Station.

Complete the verification of land origin to serve the preparation of compensation plans for projects; approve compensation and support plans to pay money to households, issue recovery notices to remaining households according to regulations for the project: 220kV transformer station Nhon Trach Industrial Park and connection, 220kV line Nhon Trach 3 Power Plant - 500kV Long Thanh transformer station and 220kV line Nhon Trach 3 - My Xuan - Cat Lai branch.

For Long Thanh district, the provincial leaders requested the district to urgently coordinate with the Southern Power Project Management Board to continue mobilizing the handover of power project sites in the area: For the 220kV transmission line project of Nhon Trach 3 Power Plant - Long Thanh 500kV Transformer Station, complete the mobilization of site handover for the remaining 4 pillar foundation locations before June 15, 2025.

Direct the People's Committee of Tam An commune and the Land Fund Development Center to complete the inventory before June 14, 2025. Direct the Department of Agriculture and Environment to sign a specific land valuation contract and approve it before June 15, 2025.

For investors of power projects, the provincial People's Committee leaders proposed to coordinate with localities to announce compensation prices to continue to mobilize households to commit to handing over the remaining foundation sites. Direct the construction unit to erect pillars and pull wires immediately at the foundation sites where the land has been mobilized to be handed over.

The Department of Industry and Trade is responsible for monitoring, urging, and reporting the progress of daily tasks to the Provincial People's Committee.

Hoang Loc

Source: https://baodongnai.com.vn/tin-moi/202506/pho-chu-tich-ubnd-tinh-duong-minh-dung-kiem-tra-cong-tac-giai-phong-mat-bang-3-du-an-dien-6230e44/


Comment (0)

No data
No data

Same category

Village on the mountain top in Yen Bai: Floating clouds, beautiful like a fairyland
Village hidden in the valley in Thanh Hoa attracts tourists to experience
Ho Chi Minh City cuisine tells stories of the streets
Vietnam - Poland paints 'symphony of light' in Da Nang sky

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product