Package No. 1 of the 500kV Lao Cai-Vinh Yen transmission line project completed foundation construction the earliest on the entire line.

Power Project Management Board 1 (EVNPMB1), Vietnam Electricity Group, said that package 1 of the Lao Cai-Vinh Yen 500kV transmission line project has completed excavation and foundation casting at all locations.

Báo Nhân dânBáo Nhân dân09/06/2025

Package No. 1, Lao Cai - Vinh Yen 500kV transmission line project includes 51 pole positions, from VT1 to VT52, passing through Bao Yen and Bao Thang districts of Lao Cai province, implemented by a consortium of Song Da Construction and Service Joint Stock Company; PC1 Group Joint Stock Company; Dong Anh Steel Pole Manufacturing Limited Company.

The locations span steep hills and narrow roads, many of which are inaccessible by motor vehicles. In addition, this year’s weather has been erratic, with the rainy season coming early, affecting the transportation of materials and equipment.

To ensure the construction progress as required, the joint venture contractor has proactively developed a multi-layer construction plan, organizing different independent construction teams. Workers are arranged to eat and rest near the construction site, minimizing travel time.

Not only taking the lead in foundation pit construction, package 1 is also the place to erect the first poles on the construction site of the entire 500kV Lao Cai-Vinh Yen line at locations VT42 and VT28.

2.jpg
The first steel poles on the entire 500kV Lao Cai-Vinh Yen line were installed.
Location of column 167 in Vinh Lac commune, Luc Yen district, Yen Bai province. (Photo: LE TIEN)

Lao Cai-Vinh Yen 500kV Transmission Line Project: Urgent construction, striving to complete by August 19

The leader of Power Project Management Board 1 said that package 1 is in the group of 10 mixed packages of the Lao Cai-Vinh Yen 500kV transmission line project. This package was officially implemented from March 10, 2025, all excavation and foundation work of this package was completed after less than 3 months of construction.

With the current progress, the joint venture contractor for package 1 will have time to proactively carry out the next steps of erecting poles and pulling wires to ensure progress according to the set plan.

Source: https://nhandan.vn/goi-thau-so-1-du-an-duong-day-500kv-lao-cai-vinh-yen-hoan-thanh-thi-cong-mong-som-nhat-tren-toan-tuyen-post885509.html


Comment (0)

No data
No data
PIECES of HUE - Pieces of Hue
Magical scene on the 'upside down bowl' tea hill in Phu Tho
3 islands in the Central region are likened to Maldives, attracting tourists in the summer
Watch the sparkling Quy Nhon coastal city of Gia Lai at night
Image of terraced fields in Phu Tho, gently sloping, bright and beautiful like mirrors before the planting season
Z121 Factory is ready for the International Fireworks Final Night
Famous travel magazine praises Son Doong cave as 'the most magnificent on the planet'
Mysterious cave attracts Western tourists, likened to 'Phong Nha cave' in Thanh Hoa
Discover the poetic beauty of Vinh Hy Bay
How is the most expensive tea in Hanoi, priced at over 10 million VND/kg, processed?

Heritage

Figure

Business

No videos available

News

Political System

Local

Product