On the occasion of the 80th anniversary of National Day, September 2, at key projects and works of the province, workers and engineers still maintain urgent construction pace to ensure progress according to plan.

Báo Lào CaiBáo Lào Cai01/09/2025

baolaocai-br_sx-1.jpg
Immediately after the start of construction, the contractor mobilized human resources and equipment to divide into many construction teams.

At the construction site of Package No. 8, leveling the ground and building technical infrastructure for plots SX1 and SX2 in the Kim Thanh - Ban Vuoc logistic area, engineers and workers of Truong Son Construction Corporation maintain the number of personnel and equipment divided into many construction teams. All are working very hard, striving to be able to hand over some locations by early December this year so that industrial production facilities that have to clear the ground to serve the Lao Cai - Hanoi - Hai Phong railway project can move here to construct and install factories.

baolaocai-br_sx-4.jpg
Workers worked urgently to ensure progress.

Mr. Vu Cong Chieu - Deputy Site Manager said that the project's advantage is that the investor and local authorities have handed over the site early. With the urgent schedule and huge workload, right after the groundbreaking ceremony on August 19, we organized the construction in the spirit of "3 shifts, 4 shifts", "working through holidays and Tet" to ensure the plan.

baolaocai-br_sx-3.jpg
Project supervisor discusses with contractor about construction plan at site.

The project of leveling the ground and constructing technical infrastructure for plots SX1 and SX2 in the Kim Thanh - Ban Vuoc logistics area to serve the site clearance for the investment project to build the Lao Cai - Hanoi - Hai Phong railway line was approved for investment by the Provincial People's Committee in Decision No. 1470/QD-UBND dated May 6, 2025, with a total investment of 106.4 billion VND from the central budget.

The project covers an area of ​​19 hectares, including leveling the ground, building an internal traffic system, installing power supply, water supply and drainage systems and other essential infrastructure.

The main objective of the project is to create a favorable site for arranging and relocating production facilities in Dong Pho Moi Industrial Park, serving the site clearance work for the Lao Cai - Hanoi - Hai Phong railway line.

This project is expected to contribute to removing infrastructure bottlenecks, promoting regional connectivity, and increasing the competitiveness of the Lao Cai international border gate area.

Along with this project, the project of leveling the ground and technical infrastructure of Ban Qua area to serve the land clearance of the investment project to build the Lao Cai - Hanoi - Hai Phong railway is also being urgently implemented. After completion, it will create a land fund to arrange for 34 enterprises related to import - export activities in Dong Pho Moi Industrial Park.

baolaocai-br_nd-2.jpg
Construction of Ngoi Dum bridge foundation pit.

At the project to upgrade and expand the IC19 intersection on the Noi Bai - Lao Cai expressway with National Highway 4D and Provincial Road 155, workers and engineers are focusing on constructing the most important item of the project, the Dum stream overpass.

The bridge is designed with reinforced concrete and prestressed reinforced concrete, including 3 spans, with a bridge deck width of 16 m.

baolaocai-br_nd-3.jpg
The recent floods have made construction in the middle of the stream difficult.

In recent days, heavy rain has continuously occurred in the area due to the influence of storm circulation, making the construction of the foundation and bridge pier difficult.

The construction site is located in the middle of a stream. Although the construction unit has built a dike to straighten the stream for construction, heavy rains have occurred continuously recently, causing water to overflow into the foundation of the pier, interrupting the construction process. Workers have to race to process steel, install formwork, and continuously pump water out of the foundation pit.

In addition, the project's starting time was delayed due to site clearance issues, so the contractor had to work overtime to make up for the delay.

baolaocai-br_nd-1.jpg
Closely monitor construction items.

Mr. Luu Van Thang - project supervisor said: To ensure quality and progress according to the design, the supervision consultant team arranges adequate personnel, closely monitors each item, controls quality, and conducts acceptance according to plan; regularly inspects the site to promptly remind and request correction of existing problems.

The project to upgrade and expand the IC19 intersection of Noi Bai - Lao Cai Expressway with National Highway 4D and Provincial Road 155, once completed, will ensure safety and convenient traffic connection from Noi Bai - Lao Cai Expressway to Lao Cai Ward with Sa Pa tourist area and improve the investment efficiency of Provincial Road 155 from Lao Cai Ward to Sa Pa tourist area.

According to the approved design, based on the existing IC19 interchange at km255 of Noi Bai - Lao Cai expressway, 3 branches currently in operation will be renovated and 1 additional branch will be built.

baolaocai-br_bs-1.jpg
Overview of the construction of the road bridge project across the Red River.

At the road bridge project across the Red River border of Bat Xat (Vietnam) - Ba Sai (China), to ensure the target of completion and handover by June 2026, construction units are racing against time to complete the first items. After more than 2 months of construction, the contractor has completed the construction of pier M2, and is constructing pier T9 and pier T8 frame.

The road bridge project across the Red River at the border of Bat Xat (Vietnam) - Ba Sai (China) is 230 m long. Each side will invest in building half of the main bridge, the tower pillar is 20 m high from the bridge surface; the bridge width is 35.3 m (including the width of the tower pillar); the total cost of building the bridge on the Vietnamese side is about 282 billion VND.

The bridge is of great significance, not only because it is located on a vital traffic route, helping to shorten the travel distance between the two localities, but also creating a great driving force for the development of trade, tourism, and cultural exchange between the two countries.

baolaocai-br_bs-2.jpg
On holidays, the construction pace is still maintained at "3 shifts, 4 shifts".

The completion of the project will open up many opportunities for economic and investment cooperation, while improving the lives of people on both sides of the border. The project is a testament to the commitment of the Vietnamese and Chinese governments to develop the transport infrastructure system in the border area, towards a region of sustainable development, peace and prosperity.

In the bustling atmosphere of the National Day holiday on September 2, the construction site still maintains a bustling pace. The bright red national flag fluttering in the wind seems to add more spirit and motivation for the workers and engineers to overcome the sun and rain.

Mr. Tran Hung Lam - Director of the Executive Board of Ban Vuoc - Ba Sai Bridge Project said: The project is of great significance and receives special attention from provincial leaders and requires high technical and aesthetic requirements, so the contractor has mobilized experienced engineers and workers to the construction site along with many modern equipment.

baolaocai-br_sequence-0100-00-00-23still001.jpg
The contractor has mobilized a team of experienced workers and engineers.

Along with these projects, Lao Cai province is currently implementing many important projects in the socio-economic development strategy, especially projects that connect regions and promote tourism and trade. The urgency and responsibility at construction sites during the National Day holiday on September 2 clearly demonstrated the enthusiastic working spirit of workers and engineers in Lao Cai. This is not only an effort to complete economic goals, but also demonstrates the determination to build the province to be increasingly developed, modern and sustainable.

Source: https://baolaocai.vn/tren-nhung-cong-trinh-khong-nghi-le-post881058.html


Comment (0)

No data
No data

Same category

Su 30-MK2 fighter jets drop jamming shells, helicopters raise flags in the capital's sky
Feast your eyes on the Su-30MK2 fighter jet dropping a glowing heat trap in the sky of the capital
(Live) General rehearsal of the celebration, parade, and march to celebrate National Day September 2
Duong Hoang Yen sings a cappella "Fatherland in the Sunlight" causing strong emotions

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product