Prime Minister inspects and urges construction of 500kV line 3 section through Nghe An

Việt NamViệt Nam24/06/2024


This morning (June 23), Prime Minister Pham Minh Chinh inspected and urged the implementation of the 500kV power transmission line project, circuit 3, Quang Trach - Pho Noi, through Nghe An province.

Prime Minister Pham Minh Chinh inspected and urged the implementation of the 500kV Power Transmission Line Circuit 3 Quang Trach - Pho Noi project, section passing through Nghe An province.
Prime Minister Pham Minh Chinh inspected and urged the implementation of the 500kV power transmission line project, circuit 3, Quang Trach - Pho Noi, section through Nghe An province.

Also going to Nghe An province were comrades: Thai Thanh Quy - Member of the Party Central Committee, Secretary of the Provincial Party Committee, Chairman of the Provincial People's Council, Head of the Provincial National Assembly Delegation; Nguyen Duc Trung - Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee; Hoang Nghia Hieu - Deputy Secretary of the Provincial Party Committee.

500kV line project, circuit 3, section through Nghe An.
Prime Minister Pham Minh Chinh inspected the construction site at the VT22 column foundation in Quynh Trang commune, Hoang Mai town.
Prime Minister Pham Minh Chinh inspected the construction site at the VT22 column foundation in Quynh Trang commune, Hoang Mai town.

The 500kV power transmission line project, circuit 3, from Pho Noi, Hung Yen province to Quang Trach, Quang Binh province, has a total length of about 519 km; the total investment is about 22,356 billion VND. The project consists of 4 component projects, starting in October 2023 and January 2024.

a
Urgent atmosphere at the construction site of the 500kV line 3 project through Nghe An.
Construction of electric poles at the foundation of VT22 pole in Quynh Trang commune, Hoang Mai town
Construction of electric poles at the foundation of VT22 pole in Quynh Trang commune, Hoang Mai town

The Prime Minister and the working delegation inspected, urged, and presented gifts to encourage the forces working at VT22 pole of the 500kV Quynh Luu - Thanh Hoa transmission line project in Quynh Trang commune, Hoang Mai town.

Prime Minister Pham Minh Chinh encouraged the construction force to erect the VT22 pole.
Prime Minister Pham Minh Chinh encouraged the construction force to erect the VT22 pole.

Delighted by the bustling construction atmosphere at the construction site, Prime Minister Pham Minh Chinh acknowledged the working spirit of the staff, engineers and workers from electricity units across the country who came to support the project implementation.

The Prime Minister and leaders of Nghe An province presented gifts to officers, engineers and construction workers at the VT22 column foundation location in Quynh Trang commune, Hoang Mai town.
The Prime Minister and leaders of Nghe An province presented gifts to officers, engineers and construction workers at the VT22 column foundation location in Quynh Trang commune, Hoang Mai town.

Highlighting the significance and importance of the 500kV power transmission line project, especially in supplying and coordinating electricity for regions during peak season, Prime Minister Pham Minh Chinh stated that there must be high determination, great efforts, drastic actions, clear people, clear work, clear time, clear products; Arranging capital sources, focusing resources on the project; When implementing, it is necessary to mobilize the entire local political system to participate, complete site clearance work in advance and mobilize local forces and means for the project. After having the site, it is necessary to urgently deploy it in a synchronous, synchronized and rhythmic manner with the spirit of "the foundation does not wait for the column, the column does not wait for the wire" and "resources originate from thinking; motivation originates from innovation; strength originates from the people", "turning nothing into something, turning difficult into easy, turning impossible into possible".

Prime Minister Pham Minh Chinh requested contractors to concentrate, mobilize human resources, equipment, and machinery, and perform synchronous construction at all locations and stages within the project scope, completing the project before June 30, 2024.

Prime Minister visits and encourages youth to participate in supporting project construction
Prime Minister visits and encourages youth to participate in supporting project construction

Here, Prime Minister Pham Minh Chinh also presented gifts, encouraged and kindly talked with local youth union members who are increasing their support for the construction. Nghe An province alone has established 74 volunteer youth teams with more than 1,100 youth union members participating in the following tasks: supporting pole erection, transporting materials from the assembly location to the installation location, supporting site clearance, moving and transporting obstacles; supporting wire pulling and traffic diversion, clearing the line corridor; supplying water to the construction teams; and disseminating the importance of the 500kV line 3 to the people.

Prime Minister praises the spirit of
Prime Minister praises the spirit of "where there is need, there is youth, where there is difficulty, there is youth"

Prime Minister Pham Minh Chinh shared that in the past, the fathers' generation did not hesitate to sacrifice hardships to fight for the liberation of the country. Today, the youth must also learn from this good tradition and contribute to the construction of the 500kV line 3. Not only for this project but also for many important projects of the country and the locality in the future.

The Prime Minister chaired a meeting with leaders of ministries, branches, 3 localities (Thanh Hoa, Nghe An, Ha Tinh) and EVN about the project.
The Prime Minister chaired a meeting with leaders of ministries, branches, localities and EVN about the project.

Working with the Electricity Group, the National Power Transmission Corporation and the two provinces of Nghe An and Ha Tinh, the Prime Minister listened to reports from units and localities on specific progress and problems that need to be resolved.

EVN Chairman Dang Hoang An speaks at the meeting
EVN Chairman Dang Hoang An speaks at the meeting

Of which, the section passing through Nghe An has so far completed casting foundations at 202/202 locations, erected 89 pole locations, is erecting 77 locations and has completed casting foundations at 36 locations, but has not yet moved to erecting poles. In the province, the wire pulling has also been completed at intersections 337 - 338 in Nam Dan district. The wire pulling is being carried out at some pole locations in Dien Chau and Yen Thanh districts.

Comrade Nguyen Duc Trung - Deputy Secretary of the Provincial Party Committee, Chairman of Nghe An Provincial People's Committee spoke at the meeting.
Comrade Nguyen Duc Trung - Deputy Secretary of the Provincial Party Committee, Chairman of Nghe An Provincial People's Committee spoke at the meeting.

In his speech, Prime Minister Pham Minh Chinh affirmed: The current state of the 500kV line 3 project has shown that there is nothing we cannot do if we have determination, solidarity, and unanimity to implement it. In addition to mobilizing the entire political system to be united, determined, and to have the entire people involved, the project also inspires the workforce across the country.

Faced with the task requirements from now until the given time, the Prime Minister proposed to launch a high-speed competition, concentrating efforts on construction with focus and key points. In particular, the Prime Minister clearly stated that there must be high determination, great efforts, drastic actions, clear people, clear work, clear time, clear products, thereby making it easy to inspect, supervise and evaluate; arrange capital sources, focus resources on the project; when implementing, it is necessary to mobilize the entire local political system to participate, complete the site clearance work in advance and mobilize local forces and means for the project, with the spirit of "unanimity, determination, all people, comprehensiveness, overallness" and efficiency.

After having the site, it is necessary to urgently deploy it in a synchronous, synchronized and rhythmic manner with the spirit of "the foundation does not wait for the column, the column does not wait for the wire" and "resources come from thinking; motivation comes from innovation; strength comes from the people", "turning nothing into something, turning difficult into easy, turning impossible into possible", promoting the spirit of "overcoming the sun, overcoming the rain", "working in 3 shifts, 4 shifts", "eating quickly, sleeping urgently", "going through holidays, holidays, Tet", "only working, no back-and-forth", synchronous construction in all locations, stages, and jobs within the scope of the project...

Prime Minister Pham Minh Chinh delivered concluding remarks at the meeting.
Prime Minister Pham Minh Chinh delivered concluding remarks at the meeting.

In the coming time, the Prime Minister requested to launch a special peak emulation period, "sprint", "lightning speed" to strive to basically complete the work of erecting poles, pulling wires, and testing by June; in July, to conduct inspections, carry out technical operation procedures, acceptance, environmental restoration and inaugurate the project...

Along with the request for localities to continue to closely participate in the project, the Prime Minister especially noted the need to inspect and care for the lives of people in the areas that must be relocated, and to ensure that their new homes are better than and equal to their old ones.

At the meeting, the Prime Minister also directly answered and directed ministries and branches to resolve and remove a number of proposals from localities.

Xuan Huong - Canh Toan


Source: https://www.truyenhinhnghean.vn/thoi-su-chinh-tri/202406/thu-tuong-kiem-tra-don-doc-thi-cong-duong-day-500kv-mach-3-doan-qua-nghe-an-7841f96/

Comment (0)

No data
No data

Same tag

Same category

Fireworks explode, tourism accelerates, Da Nang scores in summer 2025
Experience night squid fishing and starfish watching in Phu Quoc pearl island
Discover the process of making the most expensive lotus tea in Hanoi
Admire the unique pagoda made from more than 30 tons of ceramic pieces in Ho Chi Minh City

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product