1. Package name: Engineering – Procurement – Construction (EPC)
2. Scope of work : Design – Procurement – Construction (EPC) of Dung Quat Oil Refinery Upgrading and Expansion Project (Adjusted Project)
3. Contract implementation period : 37 months (from the date of contract implementation to preliminary acceptance)
4. Capital source : Investment capital for Dung Quat Oil Refinery Upgrading and Expansion Project
5. Form of contractor selection : International open bidding
6. Contractor selection method : One stage, one envelope
7. Bidding form : Not online
8. Time of issuing the Bidding Documents: 16:56 on September 3, 2025 ( Hanoi time) at the National Bidding Network System (https://muasamcong.mpi.gov.vn). Bidders download the Bidding Documents at the website of the National Bidding Network System ((https://muasamcong.mpi.gov.vn).
9. Validity of Bidding Documents : ≥ 180 days from the closing date of bidding.
10. Bid Security: Value and currency of Bid Security: USD 18,000,000; Validity period of Bid Security: ≥ 210 days from the bid closing date.
11. Place to receive Bidding Documents : Binh Son Refining and Petrochemical Joint Stock Company, 208 Hung Vuong, Nghia Lo Ward, Quang Ngai Province, Vietnam.
12. Bidding closing time : 11:10 AM, December 3, 2025 (Hanoi time)
Bid opening time: 11:20 AM, December 3, 2025 (Hanoi Time) at 208 Hung Vuong, Nghia Lo Ward, Quang Ngai Province, Vietnam.