Lam Dong urgently establishes a schedule for implementing investment projects.

On the morning of August 28, Mr. Vo Ngoc Hiep, Vice Chairman of Lam Dong Provincial People's Committee chaired a working session with Project Management Board No. 1 to listen to reports on the implementation of tasks and progress of investment projects.

Báo Lâm ĐồngBáo Lâm Đồng28/08/2025

as.jpg
Working scene

Reporting at the meeting, the leader of Project Management Board No. 1 said: The Board is managing 41 projects, with 29 projects allocated capital this year. The total disbursement value is more than 144/3,281 billion VND, reaching 4.4%.

Of which, basic construction projects: 142.6/961.7 billion VND, reaching 14.84%. Central budget allocation: 78.9/407.3 billion VND, reaching 19.38%.

Notably, projects such as: Tan Phu - Bao Loc Expressway Project has been approved and is reviewing bidding documents; Bao Loc - Lien Khuong Expressway Project has not been allocated capital this year; Agricultural Infrastructure Improvement Project has disbursed 32.8%; Ta Hoet Reservoir Project is currently suspended due to compensation issues.

so-ngong-nghiep-28.jpg
Representative of the Department of Agriculture and Environment reported at the meeting.

In addition, the Board is also assigned to implement other projects: Mo Vet Bridge Construction Project; Rural Sanitation and Clean Water Expansion Program; DT.729 Road Construction Project; DT.721 Road Upgrade Project; Cam Ly - Phuoc Thanh Road Construction Project; Investment and Construction Project to Replace 5 Weak Bridges; Waterproofing and Leakage Repair Project for the Provincial Administrative Center Building; Da Lay and Da Si Lake Canal System Project; Lien Khuong - Prenn Expressway Service Road Construction Project; Obstetrics Department Construction Project of Lam Dong Children's Hospital.

financial-28.jpg
Representatives of the Department of Finance spoke

The common problem of these projects, according to the Board's report, is that the site clearance work is slow due to many reasons. Among them, people do not agree with the compensation price and the administrative procedures are complicated.

Some projects lack capital, affecting construction progress. Some regulations and rules are not suitable to reality, causing difficulties in the implementation process.

dia-phuong-28.jpg
Local representatives speak out

The Committee recommends that the Provincial People's Committee direct relevant departments, agencies and sectors to coordinate in resolving problems related to site clearance, capital allocation, and completion of legal procedures; consider adjusting investment policies for a number of projects to suit the actual situation.

Representatives of relevant localities, departments and branches reported on the problems and difficulties of projects in the area.

Delegates also expressed their opinions that the delay in project progress, in addition to weather and objective factors, has other subjective causes; in which, the Board has not been determined to promote construction at the construction site.

lemon-vp.jpg
Chief of Office of Lam Dong Provincial People's Committee speaks at the meeting

“There is no other way, in the coming time, we need to drastically speed up the progress. Review, any project group that is not stuck must drastically speed up the progress, effectively manage and urge. Along with that, build a detailed and specific plan for each project to promote progress”, said Nguyen Nhan Ban, Chief of Office of the Provincial People's Committee.

vnhiep-28.jpg
Comrade Vo Ngoc Hiep, Vice Chairman of the Provincial People's Committee, emphasized the need to urgently establish a schedule for project implementation.

At the meeting, Vice Chairman of the Provincial People's Committee Vo Ngoc Hiep analyzed and pointed out the existing causes. He criticized the Board for not being decisive, not following the project closely, not proactively reporting to the provincial leaders to remove obstacles, leading to low disbursement of investment capital for projects.

Comrade Vo Ngoc Hiep assigned the Board to seriously improve the internal apparatus; continue to effectively implement assigned activities and tasks; and prepare adjustment documents for projects that have changed after the merger managed by the Board.

Along with that, review and adjust capital; closely coordinate with the People's Committees of communes and wards during the project implementation process. In assigning tasks and directing project implementation, the Board needs to be specific, clear about people, clear about work and consistent to closely follow progress and research and implement effectively.

He also directed that it is necessary to urgently establish a project implementation schedule, ensure disbursement of assigned capital; review projects and urge progress.

Departments and branches need to proactively guide, resolve and report to the Provincial People's Committee to immediately remove obstacles. For localities, he requested to do a good job of propaganda and mobilizing people in site clearance work.

Source: https://baolamdong.vn/lam-dong-khan-truong-lap-bang-tien-do-trien-khai-cac-du-an-dau-tu-389030.html


Comment (0)

No data
No data

Same tag

Same category

Summary of A80 training: Vietnam's strength shines under the night of the thousand-year-old capital
Hanoi traffic chaos after heavy rain, drivers abandon cars on flooded roads
Impressive moments of the flight formation on duty at the A80 Ceremony
More than 30 military aircraft perform for the first time at Ba Dinh Square

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product