The embankment combined with the traffic road of the project phase 1, nearly 1km long, has reached more than 70% of the plan.

The project to reinforce the embankment combined with the road is over 2.048km long, running along the Bo River bank through Phong Thai ward (located in Phong An ward and Phong Son commune, old Phong Dien town); the newly built section is over 1.5km long and the repaired section is over 0.5km long.

The embankment project is more than 1.7km long; of which the newly built part is more than 1.2km long. The scale of the embankment crest elevation through this area is reinforced with M200 concrete combined with a 3m wide sidewalk, paved with terrazzo tiles, arranged with green tree markers, creating a landscape; the embankment body is filled with compacted soil reaching K=0.9, the embankment roof is inclined or vertical wall combined with inclined roof reinforced with concrete.

The embankment section through Phong Son commune (old) was newly built with a length of nearly 0.3km; in which the scale of the embankment top structure changes according to the natural ground surface and is reinforced with M250 concrete, with marker posts arranged on the top of the embankment; the embankment body is filled with compacted soil reaching K=0.9 and the roof is reinforced with 30cm thick dry paving stones in a M250 reinforced concrete bracing system, below is a 10cm thick layer of crushed stone and a layer of geotextile.


Progress of 3 anti-erosion embankment sections 300m long through Phong Son commune (old) will be completed next month.

Currently, the project (phase 1) has been invested with more than 20 billion VND, speeding up the progress of the embankment combined with the newly built road of nearly 1km long and reinforcing the embankment at 3 points of 300m long through Phong Son commune (old) to finish before the flood season of the year. now .

Mr. Ho Huu Phu, Head of the Investment and Construction Project Management Board of Area 2, said that phase 1 of the project started in early 2025 and has now completed more than 70% of the plan; in the embankment section combined with the construction of the new road, the roadbed and drainage system, bridges and culverts on the route have been completed, and the asphalt pavement has been prepared... The goal of the project when completed is to ensure the stability of the Bo River bank and protect Provincial Road 11B as well as more than 150 households in the area. speak above.

News and photos: Minh Van