Vietnam.vn - Nền tảng quảng bá Việt Nam

Project 500 kV Vinh Yen transformer station is qualified and ready to be energized

(Chinhphu.vn) - The investor-level acceptance council of the National Power Transmission Corporation (EVNNPT) has just met and agreed that the Vinh Yen 500kV transformer station project and the connecting line are eligible to be energized in phase 1.

Báo Chính PhủBáo Chính Phủ19/07/2025

Dự ánTrạm biến áp 500 kV Vĩnh Yên đủ điều kiện sẵn sàng đóng điện- Ảnh 1.

Vinh Yen 500 kV substation project and connection lines are ready to be energized - Photo: VGP/Toan Thang

This is the project chosen by the Party Committee of Vietnam Electricity Group (EVN) as the project to put up a sign to welcome the 4th EVN Party Congress, term 2025-2030.

The 500kV Vinh Yen Transformer Station (TSS) project and connecting lines are special-class, group B energy projects invested by EVNNPT and assigned to manage and operate by the Northern Power Project Management Board (NPMB).

The project has a scale of building a new 500/220/35kV substation including 2 900MVA transformers, each transformer is connected to a combination of 3 single-phase transformers, capacity 300MVA.

When completed, the 500kV Vinh Yen transformer station will be connected to the 500kV Hiep Hoa - Son La line. Hiep Hoa - Viet Tri will be the transfer point between two sources of thermal power and hydropower from Son La and Hoa Binh hydropower plants and thermal power clusters in the Quang Ninh area.

This transformer station will also be connected to the 500kV Lao Cai - Vinh Yen line after the line is completed, promptly increasing the load capacity, releasing power from small hydropower plants in the Northwest region and importing electricity, contributing significantly to ensuring electricity in the Northern region during peak times of the dry season.

At the meeting, EVNNPT Deputy General Director Hoang Van Tuyen, Chairman of the Investor-level Acceptance Council, acknowledged and highly appreciated NPMB, EVNNPT Construction Investment Management Board and project participants for their efforts and overcoming many difficulties and challenges to complete phase 1 of the project.

Emphasizing that this is a very important project to meet the demand for load growth of the Phu Tho province power system; create strong links between areas in the power system, increase the ability to operate safely and stably for the national power system; reduce power loss in the transmission grid, increase the efficiency of EVN's electricity production and business. Therefore, EVNNPT leaders requested NPMB and EVNNPT's professional departments to continue to coordinate with dispatching levels to register power outage schedules in order to energize the project as soon as possible.

Based on the conclusions and proposals of the basic acceptance council and the opinions of relevant parties, the project investor acceptance council agrees to accept the project to complete related procedures to be ready for energization in the near future.

To speed up the project progress to put up a welcome sign for the Party Congress of the Group, immediately after receiving the directive, the NPMB Party Committee developed an Action Program to implement the Resolutions of the Party Committee of the Group and the Corporation to speed up the investment progress of the construction of the 500kV Vinh Yen substation and the connecting line.

Preparations for the project's plaque-mounting ceremony are being carried out urgently, thoroughly and thoughtfully. The plaque-mounting ceremony is expected to be held on July 24, 2025, contributing to creating a vibrant and practical competitive atmosphere to welcome the 4th EVN Party Congress.

Toan Thang


Source: https://baochinhphu.vn/du-antram-bien-ap-500-kv-vinh-yen-du-dieu-kien-san-sang-dong-dien-102250719071718538.htm


Comment (0)

No data
No data
PIECES of HUE - Pieces of Hue
Magical scene on the 'upside down bowl' tea hill in Phu Tho
3 islands in the Central region are likened to Maldives, attracting tourists in the summer
Watch the sparkling Quy Nhon coastal city of Gia Lai at night
Image of terraced fields in Phu Tho, gently sloping, bright and beautiful like mirrors before the planting season
Z121 Factory is ready for the International Fireworks Final Night
Famous travel magazine praises Son Doong cave as 'the most magnificent on the planet'
Mysterious cave attracts Western tourists, likened to 'Phong Nha cave' in Thanh Hoa
Discover the poetic beauty of Vinh Hy Bay
How is the most expensive tea in Hanoi, priced at over 10 million VND/kg, processed?

Heritage

Figure

Business

No videos available

News

Political System

Local

Product