Vietnam.vn - Nền tảng quảng bá Việt Nam

Độc lập - Tự do - Hạnh phúc

Synchronizing solutions to promote disbursement of public investment capital

The target is to disburse 60% of the planned public investment capital by the end of September and 100% by the end of the year. However, the disbursement progress is still slow, requiring more determination from all levels, sectors and investors.

Báo Sơn LaBáo Sơn La03/09/2025

Construction of the project to relocate residents in the urgent disaster area affected by storm No. 3 in Na Tra village, Muong La commune.

The province's total public investment capital in 2025 is more than VND 6,626 billion, including VND 315 billion transferred from 2024 and more than VND 6,310 billion planned for 2025. To date, the province has allocated more than VND 6,133 billion in detail, reaching 92.57%, with about VND 492 billion (7.43%) remaining unallocated. As for the capital disbursement progress of the whole province, by July 31, the whole province had only disbursed more than VND 1,872 billion, reaching 28.25% of the total assigned capital plan and 30.51% of the detailed allocation plan. Although it increased by more than VND 305 billion compared to June, this rate is still low compared to the requirement.

Mr. Hoang Manh Thang, Deputy Director of the Provincial Traffic Project Management Board, informed: Project progress is facing difficulties due to land clearance problems. For example, the project to renovate and upgrade National Highway 37 connecting National Highway 279D, with a total capital of more than VND 857 billion, was approved in 2021 but had to delay the progress to December 31, 2025. Currently, the project has only completed the section Km0-Km44 (Bac Yen, Pac Nga), while the section Km44-Km67+128 (Muong La) is still stuck with land clearance. The roadbed is 22.7/23.1 km, the concrete road surface is about 15.7 km. To date, the project has been granted VND 791 billion, disbursed more than VND 751 billion.

Not only large projects, but also programs to relocate residents and essential infrastructure are facing difficulties. In Muong La, the project to relocate residents in the urgent disaster area in Na Tra village, with an investment capital of 15 billion VND, has 11 households affected by land acquisition. Mr. Nguyen Chi Thanh, Vice Chairman of the Commune People's Committee, said: Compensation and support for trees and crops have been completed, and households have agreed to hand over the site. The contractor has constructed the ground leveling, internal roads, regulating tanks, and pumping stations, but has encountered difficulties due to changes in management decentralization, capital sources after merging administrative units, and construction during the rainy season. The progress is currently about 40%, with disbursement of more than 3 billion VND (up to August 24, 2025). The commune strives to complete the relocation of households to resettlement sites before November 30, 2025.

Mr. Nguyen Van Phong, Deputy Director of the Department of Finance, said: The slow disbursement is mainly due to problems in compensation, support for site clearance, difficulties in determining land origin, land use for the wrong purpose and absent land users. In addition, investment preparation is slow, some investors are not determined, many new projects have been allocated capital so they have not been implemented yet.

The target of GRDP growth of 8% in 2025 is posing the task of focusing on accelerating the progress of public investment disbursement as a key political task in the last months of the year. The Provincial People's Committee has requested agencies, units and localities to allocate capital in detail, avoid spreading, and make monthly and quarterly disbursement plans. Speed ​​up site clearance, remove land problems, strengthen field inspections, and urge contractors. Implement the "6 clear" principle (clear people, clear work, clear responsibility, clear authority, clear time, clear results) and strictly handle delaying units, avoid negativity and waste. Promote the effectiveness of 5 working groups to remove difficulties for projects and production and business. Ensure project handover and transition at the end of the district government's term, not to interrupt public investment plans. Increase investment attraction in key areas, while strictly managing planning, especially for projects that have been approved in principle.

For national target programs, the province directed to review difficulties and resolve them immediately in September; ODA projects must closely follow progress and promptly resolve problems. After signing the contract, investors must quickly make advances, prepare sufficient conditions for construction, acceptance, and payment as soon as there is volume. At the same time, the province will flexibly transfer capital from slow-moving projects to projects with good disbursement capacity.

Accelerating the disbursement of public investment capital is the key to opening up new development momentum for Son La . When determination is concretized by action, project progress is strictly controlled and responsibility is attached to each individual, Son La will effectively utilize resources, promote sustainable growth and affirm its position as the development center of the Northwest region.

Source: https://baosonla.vn/kinh-te/dong-bo-giai-phap-thuc-day-giai-ngan-von-dau-tu-cong-0AbvFvrHg.html


Comment (0)

No data
No data

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product