Urging to remove bottlenecks in land clearance for important transmission project cluster in Dong Nai

(Chinhphu.vn) - On July 16, in Dong Nai, Mr. Hoang Trong Hieu, Deputy Chief of Office of the State Steering Committee for important national programs, works and projects in the energy sector (Steering Committee) inspected the field of transmission projects to release capacity of Nhon Trach 3 and Nhon Trach 4 Power Plants.

Báo Chính PhủBáo Chính Phủ17/07/2025

The delegation included Mr. Pham Le Phu - General Director of the National Power Transmission Corporation (EVNNPT), representatives of EVNNPT's professional departments, leaders of the Southern Power Project Management Board (SPMB), and the Power Transmission Project Management Board (NPTPMB).

Đốc thúc gỡ nút thắt về mặt bằng cụm dự án truyền tải quan trọng tại Đồng Nai- Ảnh 1.

Mr. Hoang Trong Hieu, Deputy Chief of the Steering Committee Office, listened to a report on the difficulties and problems of the project cluster - Photo: EVNNPT

Project site bottleneck

To ensure the release of capacity of Nhon Trach 3 and Nhon Trach 4 Power Plants, the National Power Transmission Corporation (EVNNPT) is implementing many transmission projects. Although the local government and many households have supported, agreed, and handed over the site for construction in parallel with the BT-GPMB implementation process. However, at some locations, some households have obstructed, affecting the progress of the projects.

These are key projects, playing an important role in releasing the capacity of Nhon Trach 3 and Nhon Trach 4 Power Plants, strengthening grid connectivity, transmitting capacity to serve the socio -economic development of the southern provinces, including Dong Nai province. When the projects come into operation, they will contribute to ensuring national energy security and increasing local budget revenue.

Reporting at the inspection, the representative of the Southern Power Project Management Board (SPMB) - the unit assigned to manage and operate the 220kV Nhon Trach 3 Power Plant - 500kV Long Thanh Substation project said: The project passes through Dai Phuoc, Phuoc An, Nhon Trach and An Phuoc communes, Dong Nai province. The plan is to energize in the third quarter of 2025.

Up to now, 59/87 foundation positions have been mobilized and handed over, 50/87 foundation positions have been cast, 30/87 pillars have been erected and the wire pulling is being organized.

The biggest bottleneck of this project is location number 2. This is a very important location (the location shares a pole with 4 lines: 2 lines of 220kV Nhon Trach 3 line - 500kV Long Thanh transformer station and 2 lines of 220kV Nhon Trach 3 line - My Xuan - Cat Lai branch), SPMB is deploying the erection of poles to pull wires to serve the energization work.

However, at this location, the local residents prevented the construction of poles and ropes, although the local authorities had invited them many times, the residents did not cooperate.

Regarding the 220kV Nhon Trach 3 - My Xuan - Cat Lai transmission line project, a representative of NPTPMB - the unit assigned to implement the project said: The project passes through Dai Phuoc and Phuoc An communes, Dong Nai province. The plan is to energize in July 2025.

Up to now, the project has mobilized the handover of 11/11 foundation locations and safety corridors. Construction has been basically completed, waiting for completion of location 02 (belonging to Nhon Trach 3 220kV line - Long Thanh 500kV substation) to connect to Nhon Trach 3 Power Plant distribution yard.

Regarding the Long Thanh - High-tech 220kV line project, the SPMB representative said: According to the project plan, the energization will be in December 2025. The project has completed the survey work. The people's meeting has been held, but the compensation plan has not been completed and approved.

For the 220kV Nhon Trach Industrial Park Substation and the connection, the scale of construction of the 220kV Substation, capacity of 250MVA in Nhon Trach district. The plan is to complete energization in December 2025.

Up to now, the project has mobilized and handed over 27,260/35,627m2 of land. At the same time, the pump house control house, guard house, rest house, fire protection water tank have been constructed; the foundation of distribution yard equipment, cable ditches, and fences are being completed. Currently, the project has not yet been approved for the BT-GPMB plan, so the money has not been paid to the households.

Đốc thúc gỡ nút thắt về mặt bằng cụm dự án truyền tải quan trọng tại Đồng Nai- Ảnh 2.

Location No. 2 of the 220kV Nhon Trach 3 Power Plant - Long Thanh 500kV Substation line project is the location facing land clearance problems - Photo: VGP/Toan Thang

Need drastic local involvement

At the site inspection, Mr. Hoang Trong Hieu, Deputy Chief of Office of the State Steering Committee for important national programs, works and projects, key to the energy sector, emphasized that this is a transmission project cluster of great significance to the national power system.

After the projects are completed, the capacity of Nhon Trach 3 and Nhon Trach 4 Power Plants will be released into the national power system, contributing to increasing the total power source capacity by more than 1,600 MW to serve the country's socio-economic development and people's lives.

In the past time, with the direction of the Prime Minister, Deputy Prime Minister, State Steering Committee for important national programs, works and projects, key energy sector, Ministry of Industry and Trade , ministries, branches, Provincial Party Committee, Dong Nai Provincial People's Committee, departments, branches, localities, the support of people with projects passing through have provided maximum support for the units to speed up the construction of the projects.

However, the progress of the projects has not yet met the requirements, while Nhon Trach 3 Power Plant has completed the test run to be ready for commercial power generation in August 2025.

If the progress of power transmission projects is not on schedule, the power source capacity will not be released in time, causing waste. Therefore, Mr. Hoang Trong Hieu requested that EVNNPT continue to coordinate closely with local authorities to focus on removing obstacles, and at the same time actively propagate and mobilize people to agree.

In case the calculation is correct and complete but the household deliberately opposes, it is necessary to report to Dong Nai province to ensure security and order during the construction process, especially at location number 2.

Mr. Hoang Trong Hieu also added that these are national key projects, included in the list of the Steering Committee for monitoring. The Steering Committee will consult with Dong Nai province to take drastic action, focusing on removing obstacles in land clearance in July 2025 to soon complete the project to meet the requirements.

At the site inspection, EVNNPT General Director Pham Le Phu requested SPMB and NPTPMB to regularly inspect and urge contractors to focus resources and speed up construction progress according to the set plan and commitments.

At the same time, proactively coordinate closely with local authorities and relevant units to implement appropriate solutions to accelerate site clearance and compensation work to hand over the entire site to the construction contractor in July 2025. During the implementation process, if there are any difficulties or problems beyond the authority, it is necessary to promptly report and propose to EVNNPT for consideration and resolution to ensure the quality and progress of the project.

EVNNPT General Director also requested the contractor to focus on human resources, vehicles, and machinery to speed up construction progress. Any column or anchorage area with available space needs workers to erect columns and pull wires immediately.

Toan Thang


Source: https://baochinhphu.vn/doc-thuc-go-nut-that-ve-mat-bang-cum-du-an-truyen-tai-quan-trong-tai-dong-nai-102250717105829941.htm


Comment (0)

No data
No data
Magical scene on the 'upside down bowl' tea hill in Phu Tho
3 islands in the Central region are likened to Maldives, attracting tourists in the summer
Watch the sparkling Quy Nhon coastal city of Gia Lai at night
Image of terraced fields in Phu Tho, gently sloping, bright and beautiful like mirrors before the planting season
Z121 Factory is ready for the International Fireworks Final Night
Famous travel magazine praises Son Doong cave as 'the most magnificent on the planet'
Mysterious cave attracts Western tourists, likened to 'Phong Nha cave' in Thanh Hoa
Discover the poetic beauty of Vinh Hy Bay
How is the most expensive tea in Hanoi, priced at over 10 million VND/kg, processed?
Taste of the river region

Heritage

Figure

Business

No videos available

News

Political System

Local

Product