Vingroup is licensed to conduct geological survey drilling for the metro project connecting the center of Ho Chi Minh City with Can Gio.

Vingroup Corporation is permitted to conduct geological survey drilling to serve the design of the urban railway project connecting the center of Ho Chi Minh City with Can Gio district.

Báo Đầu tưBáo Đầu tư26/06/2025

The Ho Chi Minh City Department of Construction has just granted a construction permit to Vingroup Corporation to conduct geological survey drilling to serve the design of the urban railway project connecting the center of Ho Chi Minh City with Can Gio district.

According to the construction permit issued by the Department of Construction, Vingroup is allowed to conduct geological surveys at 10 locations.

Specifically, at Nguyen Van Linh Street, District 7 (1 drilling point); Nguyen Luong Bang Street, District 7 (2 drilling points); Rung Sac Street, Can Gio District (7 drilling points).

The construction permit is valid from June 20, 2025 to July 20, 2025 and construction can only be carried out between 10:00 p.m. and 5:00 a.m. the following day. The maximum construction time at each borehole location is 6 days.

The metro line connecting the center of Ho Chi Minh City to Can Gio is expected to run along the current Rung Sac road. Photo: Viet Dung.

The Ho Chi Minh City Department of Construction requires investors to be responsible for directing construction units to fully implement traffic safety measures such as arranging signs, warning lights, and traffic control forces.

After receiving the site, the construction unit must be responsible for traffic safety and subject to inspection and control by the road management unit and other competent authorities.

Previously, in early May 2025, the Ho Chi Minh City People's Committee approved Vingroup Corporation to research and prepare a proposal for the railway project connecting the city center with Can Gio district under the public-private partnership (PPP) method.

Vingroup Corporation must complete the project proposal dossier and submit it to the competent authority within 1 year from April 28, 2025.

In case the project proposal is not approved by the competent authority, or is not completed within 1 year, the document will be invalid. Vingroup Corporation shall bear all risks and expenses incurred.

The urban railway project connecting the city center to Can Gio was proposed by Vingroup with a length of 48.5 km.

Regarding the implementation progress, the investor proposed to prepare for investment from 2025. Construction will be carried out from 2026 to 2028. It is expected that the project will be tested and handed over in 2028.


Source: https://baodautu.vn/vingroup-duoc-cap-phep-khoan-khao-sat-dia-chat-du-an-metro-noi-trung-tam-tphcm-voi-can-gio-d314454.html


Comment (0)

No data
No data

Same tag

Same category

Summary of A80 training: Vietnam's strength shines under the night of the thousand-year-old capital
Hanoi traffic chaos after heavy rain, drivers abandon cars on flooded roads
Impressive moments of the flight formation on duty at the A80 Ceremony
More than 30 military aircraft perform for the first time at Ba Dinh Square

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product