Prime Minister Pham Minh Chinh inspects the progress of Long Thanh airport

On the afternoon of August 2, Prime Minister Pham Minh Chinh led a Central working delegation to inspect the construction progress of Long Thanh airport (Dong Nai province).

Báo Sài Gòn Giải phóngBáo Sài Gòn Giải phóng02/08/2025

The Prime Minister and the working delegation inspected the construction progress of the second runway worth more than VND 2,500 billion, undertaken by a consortium of strong contractors including ACC - Truong Son - Vinaconex - Vinadic - ACJC647 - Khanh Thien - VTG.

At the construction site, there are 283 engineers, workers and 127 machines and equipment, simultaneously deploying construction teams of foundation, road base, drainage system and M150 cement concrete layer; the value of the completed volume reached 68.6 billion VND and the materials gathered on site reached about 100 billion VND.

z6866662400647_d3d27841c481bc4071a4b86240bc907a.jpg
Prime Minister Pham Minh Chinh inspects the progress of Long Thanh airport

Currently, Vietnam Airlines Corporation (ACV) has selected a contractor under a special mechanism, starting construction of the second runway on May 30, expected to be completed in the first half of 2026.

z6866662407302_2e3c90e1f57978aaa80c2ecaf4cef331.jpg
Prime Minister Pham Minh Chinh asked contractors to speed up the construction of airport terminals and the second runway at Long Thanh airport.

The delegation then continued to inspect the 5.10 package, the construction of the passenger terminal undertaken by the Vietur consortium. This is the “heart” of the entire Long Thanh airport project phase 1, with the basic goal of completing construction by the end of 2025 and operating in the first half of 2026.

z6866662395299_f5ba0cb0350f1c4f3b3d4c75d452bc29.jpg
During the inspection, Prime Minister Pham Minh Chinh inspected the progress of runway 2 and terminal of Long Thanh airport.
z6866662418927_c655b085f5853ea4f77451a5a1586a8c.jpg
Contractors are mobilizing human resources to construct Long Thanh airport.

Currently, the station construction site has about 4,700 engineers, workers and more than 1,000 pieces of machinery and equipment; the completed volume is about 16,002 billion VND, the underground and above-ground floors from 1 to 4 have completed the structure; the central roof steel structure is 99% complete, the first roof has been completed.

According to the plan, the entire construction, architectural completion, MEP, ICT and terminal equipment installation will be completed before December 19, 2025 to enter the testing phase, ready for operation.

z6866662388036_51328ba50acc33ec3e81ab09327d6cfd.jpg
Vehicles and machinery mobilized to construct Long Thanh airport

Prime Minister Pham Minh Chinh visited, encouraged and presented gifts to officers, engineers and workers working at the Long Thanh airport project site and praised the efforts of the team of engineers and workers who worked day and night on the construction site in harsh weather conditions.

Prime Minister Pham Minh Chinh emphasized that this is a symbolic project of a new development stage not only for the Southeast region but also for the whole country, so he requested contractors and construction management units to continue promoting the construction spirit, ensuring quality, safety and progress.

Source: https://www.sggp.org.vn/thu-tuong-pham-minh-chinh-kiem-tra-tien-do-san-bay-long-thanh-post806623.html


Comment (0)

No data
No data
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony

Heritage

Figure

Business

No videos available

News

Political System

Local

Product