Sand mines approved by the People's Council of Soc Trang province to be put into exploitation include: MS08 mine in Song Phung commune, Dai Ngai town (Long Phu district) and An Thanh 1 commune (Cu Lao Dung district), area 35ha, reserve of about 700,000m 3 ; MS09 mine in Long Phu town (Long Phu district) and An Thanh Tay commune, Dai An 1 commune (Cu Lao Dung district), area 100ha, reserve of 600,000m 3 ; MS12 mine in An Lac Tay commune (Ke Sach district), area over 32.4ha, reserve of over 185,000m 3 ; MS02 mine in Phong Nam commune, An Lac Tay commune (Ke Sach district), area 3ha, reserve of 63,000m 3 .
The total reserve of the 4 river sand mines above is more than 1.5 million m3 , with an area of about 170 hectares. The above sand mines will complete procedures to hand over to the contractor for exploitation and supply to Component 4 Project, meeting the construction progress of the project.
Source: https://www.sggp.org.vn/bo-sung-4-mo-cat-cho-duong-cao-toc-chau-doc-can-tho-soc-trang-post800902.html