Vietnam.vn - Nền tảng quảng bá Việt Nam

Road project over 70 billion behind schedule extended until end of 2024

Báo Giao thôngBáo Giao thông16/02/2024


On February 16, the Department of Transport of Dak Nong province said that the Provincial People's Committee has just issued a document agreeing to extend the project implementation period and contract implementation progress for the construction package of the project: Road from village 1 to the Mong ethnic minority area of Nam Tang village, Dak R'La commune, Dak Mil district to Cu K'Nia commune, Cu Jut district, Dak Nong province until the end of December 2024.

Đắk Nông: Đường hơn 70 tỷ chậm tiến độ được gia hạn đến cuối năm 2024- Ảnh 1.

Dak Nong province extended the progress of the project "Road from village 1 to the Mong ethnic minority area of Nam Tang village, Dak R'La commune, Dak Mil district to Cu K'Nia commune, Cu Jut district" until the end of December 2024. Photo: NH

The Provincial People's Committee assigned the Dak Nong Provincial Construction Investment Project Management Board (investor) to organize the implementation of procedures to adjust the project implementation time as a basis for adjusting the contract implementation progress and related contents according to regulations.

At the same time, the investor is required to direct the contractor to speed up the construction progress on schedule, organize acceptance, and hand over the project for use. The Department of Transport monitors and supervises the project implementation progress of the investor and is responsible for the accuracy and legal basis of the contents advised and proposed by the unit.

As Giao thong Newspaper reported in the article "People suffer because of the missed deadline of the 70 billion VND road", in 2021, the traffic road project from Dak R'la commune (Dak Mil) to Cu K'nia commune (Cu Jut) started construction. The project's goal is to create connectivity for remote areas of Dak R'la and Cu K'nia communes to trade and develop socio-economy .

However, since the commencement of construction, the project has not been completed. The road section through Nam Tang village is under construction, the road surface is sunken and deformed, seriously affecting the travel of the people. Especially in the rainy season, the road surface is plowed and muddy, making it impossible for people to travel or transport agricultural products.

The traffic project from village 1 to the Mong ethnic minority area of Nam Tang village (Dak R'la commune, Dak Mil district) to Cu K'nia commune (Cu Jut district) was approved by the Dak Nong Provincial People's Committee for the contractor selection plan in February 2021, and started construction in September 2021.

The above project has a total investment of more than 71 billion VND from the local budget, the entire route length is 12km, invested according to grade VI road standards, with a roadbed of 3.5m concrete, reinforced 1.25m sidewalk on each side.

The project is invested by the Dak Nong Provincial Construction Investment Project Management Board (DAMB). Package No. 9 is constructed by the joint venture of Thinh Thanh Dak Nong Company Limited and Thanh Cong Construction Company Limited.



Source

Comment (0)

No data
No data
PIECES of HUE - Pieces of Hue
Magical scene on the 'upside down bowl' tea hill in Phu Tho
3 islands in the Central region are likened to Maldives, attracting tourists in the summer
Watch the sparkling Quy Nhon coastal city of Gia Lai at night
Image of terraced fields in Phu Tho, gently sloping, bright and beautiful like mirrors before the planting season
Z121 Factory is ready for the International Fireworks Final Night
Famous travel magazine praises Son Doong cave as 'the most magnificent on the planet'
Mysterious cave attracts Western tourists, likened to 'Phong Nha cave' in Thanh Hoa
Discover the poetic beauty of Vinh Hy Bay
How is the most expensive tea in Hanoi, priced at over 10 million VND/kg, processed?

Heritage

Figure

Business

No videos available

News

Political System

Local

Product