Song Tranh Hydropower Company overhauls H1 generator and 220kV station

Việt NamViệt Nam16/07/2024


img_9880.jpg
Engineers inspect and maintain equipment of Unit H1 of Song Tranh 2 Hydropower Plant. Photo: XUAN LAN

Accordingly, from July 11 to August 9, 2024, unit H1 will be overhauled according to the technical plan and repair schedule approved by superiors.

The representative of Song Tranh Hydropower Company said that with the goal of restoring the equipment's features according to the original design parameters after the overhaul, ensuring the equipment operates safely and continuously until the next major repair cycle, this year's overhaul the company will focus on maintaining, repairing, and replacing equipment systems after more than 15 years of operation.

Workshop engineers are maintaining oil pumping equipment for the hydraulic system of Song Tranh 2 Hydropower Plant. Photo: N.T.B
Maintenance of oil pump equipment for the hydraulic system of Song Tranh 2 Hydropower Plant. Photo: XUAN LAN

The overhaul of unit H1 was carried out using the reliability-centered maintenance (RCM) method; at the same time, the equipment system status was analyzed and evaluated to select a reliability-centered maintenance method for the plant.

Overhaul items of unit H1 include: repair and maintenance of unit equipment, main transformer (H1-T1); distribution station and 220kV overpass; repair of factory central control system; AC and DC self-contained equipment system; compressed air system...

At the same time, unit H1 will be tested and repaired for any existing problems and defects in the equipment system discovered during operation as well as during the unit's shutdown for inspection.

Overview of inspection and maintenance at Unit H1 of Song Tranh 2 Hydropower Plant. Photo: N.T.
Overview of inspection and maintenance at H1 unit. Photo: XUAN LAN

Previously, the company registered to isolate unit H1 with the National Power System Control Center; surveyed and established a repair list, technical plan and organized the purchase of equipment and materials according to regulations.

Completing the repair and maintenance of the 220kV distribution station in June 2024 and implementing the overhaul of unit H1 as planned will improve the reliability of the equipment system for safe and stable operation, contributing to the successful completion of the 2024 production and business plan of Song Tranh Hydropower Company.



Source: https://baoquangnam.vn/cong-ty-thuy-dien-song-tranh-dai-tu-to-may-h1-va-tram-220kv-3137990.html

Comment (0)

No data
No data

Same tag

Same category

More than 30 military aircraft perform for the first time at Ba Dinh Square
A80 - Rekindling a proud tradition
The secret behind the nearly 20kg trumpets of the female military band
Quick review of how to get to the 80th Anniversary Exhibition of the Journey of Independence - Freedom - Happiness

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product