This is the final stage to evaluate the load-bearing capacity and safety of the bridge before it is officially put into operation. Dozens of vehicles have been put through load testing on Rach Mieu 2 Bridge.
According to Mr. Tran Van Thi, Director of My Thuan Project Management Board, as of today, the overall progress of the project has reached 99%. This figure reflects the tireless efforts of hundreds of workers and technicians over the past time.
The Rach Mieu 2 Bridge Project has a total investment of over VND 6,810 billion; it is not only an important traffic project, but also has profound socio -economic significance. The 1,971.2 m long cable-stayed bridge with a 4-lane grade III delta road will significantly reduce pressure on the current Rach Mieu Bridge; especially reducing traffic congestion on weekends and holidays. |
With more than 35 construction sites, 100 pieces of equipment, 350 workers and 70 technical staff working in 3 shifts, 4 teams, the construction site still maintains a high pace to ensure progress.
It is expected that before September 2, the bridge will be officially inaugurated and put into operation, opening a new chapter for traffic connecting the two western provinces.
With 99% progress completed and the load test going smoothly this morning, Rach Mieu 2 Bridge is gradually preparing for the important day of inauguration, contributing to promoting the development of the entire region.Source: https://baoapbac.vn/kinh-te/202507/can-canh-thu-tai-cau-rach-mieu-2-truoc-gio-khanh-thanh-1047519/