Da Ham Reservoir |
Accordingly, in the 2025 - 2027 period, the operation management road will be repaired and upgraded with a total length of about 2,000 m. Of which, the road section from DT.721 to the dam has an asphalt concrete surface; the road section from the left shoulder of the dam to the spillway has a concrete structure on a graded layer.
At the same time, solidify, repair and upgrade 1,350 m of the canal system. Specifically, the main canal is rebuilt along the old route with a length of about 100 m; the N2 canal demolishes 450 m of damaged and degraded stone canal to rebuild the canal with a cross-section size of the U-shaped canal with the largest bottom width of about 0.8 m and the largest channel height of about 0.8 m. The N1-3 canal is solidified with a length of 800 m with a cross-section size of the U-shaped canal with the largest bottom width of about 1 m and the largest channel height of about 0.8 m...
Source: https://baolamdong.vn/kinh-te/202506/40-ty-dong-nang-cap-ho-chua-nuoc-da-ham-1d771e9/