Khanh Hoa to hand over site for Nuclear Power Plant Project in October 2025

Khanh Hoa Provincial People's Committee aims to basically complete compensation, support, and resettlement in September and finish paying and handing over the site of the Nuclear Power Plant project in October 2025.

Báo Sài Gòn Giải phóngBáo Sài Gòn Giải phóng29/08/2025

dasua-5819.jpg
Meeting scene. Photo: HIEU GIANG

On August 29, Khanh Hoa Provincial People's Committee held a meeting of the Provincial Steering Committee to implement the Nuclear Power Plant project.

Speaking at the direction, Vice Chairman of Khanh Hoa Provincial People's Committee Trinh Minh Hoang requested relevant agencies and localities to urgently speed up the site clearance progress, considering this an urgent task: basically complete compensation, support, and resettlement in September and finish payment and handover of the site in October 2025.

Vice Chairman of the Provincial People's Committee Trinh Minh Hoang requested the Department of Agriculture and Environment of Khanh Hoa province to dispatch officials to support the commune in appraising compensation and resettlement plans; review the implementation plan of the commune level, make a comprehensive assessment, point out difficulties and obstacles, and report to the Provincial People's Committee before September 4.

Khanh Hoa Provincial Department of Finance is assigned to monitor and guide relevant localities to accelerate the disbursement of public investment capital; People's Committees of relevant communes develop specific site clearance plans, closely following the targets; The Provincial Vietnam Fatherland Front Committee coordinates with relevant agencies to strengthen propaganda and mobilize people to promptly hand over the site so that the project can be implemented smoothly...

dasua-2.jpg
Deputy Prime Minister Bui Thanh Son and the Central working delegation listened to a report on information on the Nuclear Power Plant project, July 2025. Photo: HIEU GIANG

To implement the Nuclear Power Plant project , in fact, it is necessary to reclaim a total area of ​​more than 1,130 hectares with 1,153 households. Of which, the total area of ​​the 2 plants is 815.03 hectares (plant 1 is 409.53 hectares and plant 2 is 405.5 hectares); the total area of ​​the 2 plant resettlement areas is 119.25 hectares, the residential area is 13.4 hectares, the cemetery area is about 22.27 hectares, the pumping station area is 0.59 hectares, and the resettlement area is about 159.6 hectares.

According to the Department of Industry and Trade of Khanh Hoa province, with the spirit of urgency and determination, striving to complete the project within 5 years according to the direction of the Central Government; all levels and sectors of the province have focused on implementing specific tasks, many tasks have achieved positive results, meeting the schedule.

However, there are still some difficulties and obstacles in carrying out the tasks as directed by the Prime Minister ...

Source: https://www.sggp.org.vn/khanh-hoa-ban-giao-mat-bang-du-an-nha-may-dien-hat-nhan-trong-thang-10-2025-post810808.html


Comment (0)

No data
No data

Same tag

Same category

Su 30-MK2 fighter jets drop jamming shells, helicopters raise flags in the capital's sky
Feast your eyes on the Su-30MK2 fighter jet dropping a glowing heat trap in the sky of the capital
(Live) General rehearsal of the celebration, parade, and march to celebrate National Day September 2
Duong Hoang Yen sings a cappella "Fatherland in the Sunlight" causing strong emotions

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product