The decision stated that due to the impact of heavy rain from June 20 to June 23; from July 3 to July 13 and from July 21 to July 22 this year, the positive slope on Provincial Road 294B in the communes of Tam Tien, Xuan Luong, Quang Trung, section Km10-Km42, collapsed. This situation greatly affects the safety of the construction and traffic safety of vehicles traveling on the route.
Landslide point on provincial road 294B passing through Tam Tien commune. |
Accordingly, the Chairman of the Provincial People's Committee assigned the People's Committees of Tam Tien, Xuan Luong and Quang Trung communes to organize site clearance and hand over to the Bac Ninh Provincial Traffic and Agriculture Project Management Board No. 1 (the unit managing and implementing the construction of emergency works) to organize emergency handling of the incident.
Focus on implementing measures to ensure people's safety in natural disaster situations; warn, monitor, guide and proactively restrict or prohibit people and vehicles from entering dangerous areas.
The Management Board of Bac Ninh Province's Traffic and Agriculture Project No. 1 regularly updates reports on the handling situation and progress of the incident; immediately deploys measures to ensure traffic safety, overcome traffic disruptions, and ensure smooth traffic to serve the people. At the same time, coordinates with the People's Committees of the above communes to organize site clearance to promptly handle the incident.
The tasks and requirements for the project are to organize the construction of clearing the landslide area and digging to treat the positive slope area that is at risk of further landslides; repairing damaged road surfaces, and adding traffic safety systems if necessary. At the same time, cutting floors, digging to expand the slope to ensure technical standards, and completing the stairway system.
Investment cost of 12.98 billion VND from the provincial budget reserve in 2025; expected completion time before November 30 this year.
The Bac Ninh Provincial Traffic and Agriculture Project Management Board No. 1 proactively coordinates with departments, branches and localities to organize the implementation of investment management work for the above-mentioned emergency construction project to ensure quality, progress, savings, no loss and compliance with legal regulations.