Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee Ta Anh Tuan listened to the units report on the project implementation status. |
According to the Management Board of Investment and Construction Projects in the Eastern Region of the province, the project is 21.6km long, connecting Tuy Hoa ward and the communes of Tuy An Nam, O Loan and Tuy An Dong. The roadbed is 42m wide, with the section from Km6 to Km10+800 having a roadbed width of 52m.
Along the route, two bridges across the river, An Hai Bridge and Dong Nai Bridge, have been built. Up to now, the localities have handed over about 50% of the construction site, which has not met the set plan. The construction units are focusing on implementing the construction, paving about 2km of asphalt; completing the roadbed and foundation of about 5km.
Chairman of the Provincial People's Committee Ta Anh Tuan requested the locality to complete site clearance in September. |
After directly inspecting the entire route, Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee Ta Anh Tuan requested localities and the Land Fund Development Center to urgently complete site clearance work and hand over to the investor and construction unit to implement the project.
In particular, for agricultural land areas, localities must hand over before August 15, and complete all site clearance work by September. For resettlement areas, localities must complete in October for people to receive. At the same time, units need to step up propaganda and mobilization to raise awareness and create consensus among people during the project implementation process.
Construction of coastal road in the eastern region of Dak Lak province. |
The coastal road is not only a driving force for marine economic development, but also creates land funds, connects urban areas, industrial parks, seaports and airports, contributing to the completion of the coastal traffic axis connecting Gia Lai - Dak Lak - Khanh Hoa provinces; creating a driving force for economic development in the eastern region of the province.
"With the available site, construction units need to speed up progress; focus on human resources, vehicles, and take advantage of favorable weather to complete the project on schedule, especially the delayed sections. The investor monitors the progress weekly and promptly advises the Provincial People's Committee to handle any arising issues. At the same time, ensure the quality and safety of the project; do not let the pressure of progress affect the quality and aesthetics of the project", Chairman of the Provincial People's Committee Ta Anh Tuan directed.
Source: https://baodaklak.vn/kinh-te/202507/chu-tich-ubnd-tinh-ta-anh-tuan-kiem-tra-tinh-hinh-thuc-hien-tuyen-duong-bo-ven-bien-4860927/