Alternate member of the Party Central Committee, Standing Deputy Secretary of the Provincial Party Committee, Chairman of the People's Council of Dong Nai province Ton Ngoc Hanh spoke at the meeting. Photo: Pham Tung |
According to the Department of Finance, currently, in the province, there are 29 works and projects included in the list of key works and projects. Of these, there are 13 public investment projects, 6 investment projects in the form of public-private partnership (PPP), 10 projects with non-budgetary investment capital and projects and plans.
Alternate member of the Party Central Committee, Standing Deputy Secretary of the Provincial Party Committee, Chairman of the People's Council of Dong Nai province Ton Ngoc Hanh delivered a concluding speech at the meeting. Photo: Pham Tung |
With 13 public investment projects with a total capital of over 53.6 trillion VND, there are currently 6 projects under construction, 7 projects are carrying out investment procedures. The common difficulties and problems of these projects are mainly in compensation and site clearance. Some projects are facing difficulties in sourcing construction foundation materials.
Deputy Secretary of the Provincial Party Committee, Chairman of the Dong Nai Provincial People's Committee Vo Tan Duc spoke at the meeting. Photo: Pham Tung |
For projects implemented under the PPP form with a total capital of more than 117 trillion VND, investment procedures are being carried out. For these projects, the main difficulties and obstacles are in the implementation process and legal basis for implementation due to Law No. 57/2024/QH15 and Law No. 90/2025/QH15 being amended, supplemented and abolished. Many contents related to the order, procedures, dossier content, appraisal content, payment methods, detailed regulations on contract types make it difficult to implement the projects.
Member of the Provincial Party Standing Committee, Head of the Internal Affairs Committee of Dong Nai Provincial Party Committee Nguyen Minh Hoi spoke at the meeting. Photo: Pham Tung |
The remaining projects are implementing investment procedures and encounter some difficulties and problems in compensation and site clearance for project implementation, and problems with the authority to approve planning adjustments (not yet decentralized).
Provincial Party Committee member, Vice Chairman of Dong Nai Provincial People's Committee Ho Van Ha speaks at the meeting. Photo: Pham Tung |
To speed up the progress of projects, the Provincial People's Committee requested that investors proactively coordinate with localities and regional land fund development centers to accelerate compensation and site clearance. The Departments of Construction, Finance, Agriculture and Environment promptly handle problems related to procedures and documents of key projects and other public investment projects, and prioritize the application of "green channels" to carry out administrative procedures related to public investment projects.
Member of the Provincial Standing Committee, Party Secretary, Chairman of the People's Council of Long Thanh commune Duong Minh Dung spoke at the meeting. Photo: Pham Tung |
For projects implemented under the PPP form, the Provincial People's Committee assigned the Department of Finance and the Department of Construction to apply legal regulations for temporary implementation. Along with that, promptly update guiding regulations, review, and advise the Provincial People's Committee to make appropriate adjustments.
Concluding the meeting, Alternate member of the Party Central Committee, Standing Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Council Ton Ngoc Hanh suggested: Leaders, agencies and units, with the highest sense of responsibility, spend more time to handle work. Functional agencies must coordinate smoothly to speed up the progress of projects. It is necessary to identify this as an important task of the whole province, a common responsibility of the entire political system, not to shirk responsibility but to share responsibility. From there, propose synchronous solutions to remove difficulties and obstacles, speed up the completion of projects to serve the development needs of the province.
"If Long Thanh International Airport comes into operation but the connecting roads are not completed, the province will lose its development advantages" - Alternate member of the Party Central Committee, Standing Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Council Ton Ngoc Hanh cited.
Member of the Provincial Standing Committee, Party Secretary, Chairwoman of the People's Council of Binh Phuoc Ward Giang Thi Phuong Hanh spoke at the meeting. Photo: Pham Tung |
Comrade Ton Ngoc Hanh also agreed to report to the Provincial Party Committee Standing Committee to propose establishing a Steering Committee to implement projects at the commune and ward levels, first of all for key projects and works.
Pham Tung
Source: https://baodongnai.com.vn/kinh-te/202509/can-giai-phap-dong-bo-de-day-nhanh-tien-do-cac-cong-trinh-du-an-trong-diem-8580805/