Vietnam.vn - Nền tảng quảng bá Việt Nam

Độc lập - Tự do - Hạnh phúc

Leaders of Nghe An Electricity Company inform about the progress of power restoration

Storm No. 5 made landfall in Nghe An on the evening of August 25, causing severe damage to the power grid, leaving many areas in the province without electricity. In this situation, Nghe An Newspaper, Radio and Television had a quick interview with Mr. Le Quang Thanh - Deputy Director of Nghe An Electricity Company to inform about the extent of the damage as well as the progress of troubleshooting.

Báo Nghệ AnBáo Nghệ An26/08/2025

PV : Could you tell us about the current situation, how much damage has Nghe An's electricity industry suffered due to the impact of storm No. 5?

Mr. Le Quang Thanh: Storm No. 5, which made landfall in Nghe An on the evening of August 25, was a major storm, causing very heavy damage to the power grid system in the province. Immediately after the storm passed, Nghe An Electricity Company directed its affiliated units to urgently carry out inspections, isolate the incident area, and organize forces to fix it. The number one goal is to restore power as soon as possible to serve people's lives, as well as production and business establishments and hospitals.

PV: Currently, which area has the most widespread power outage, sir?

Mr. Le Quang Thanh: The most affected areas include Vinh City, Cua Lo, Nghi Loc, Dien Chau, Quynh Luu, Yen Thanh, and Hoang Mai Town (old). In Vinh City (old) in particular, widespread power outages were mainly caused by trees falling on power lines, breaking wires and power poles.

PV: So how is the progress of the fix? How has the company mobilized human resources to handle it?

Mr. Le Quang Thanh: Following the direction of the Northern Power Corporation and the Company's leadership, we aim to restore the entire medium-voltage grid in the old Vinh City area and some key areas today (August 26). After that, we will continue to handle the low-voltage lines, gradually restoring power to households according to the motto "handle to where, supply power to there".

Regarding manpower, the Company has mobilized all officers and employees in the unit. At the same time, the Corporation also sent 3 Deputy General Directors directly to Nghe An to direct the recovery work. At the same time, shock troops from other power companies have also been mobilized to support. We are making every effort to restore power to the people as soon as possible.

GENERAL REPORT OF NGHE AN ELECTRICITY COMPANY

1. Impact, damage:

- Impacts on power grids, power stations, and constructions:

Affecting the power supply and causing damage to the assets of the electricity industry such as: many locations of medium and low voltage power poles are tilted, broken, landslides...etc.

- Impacts on local power supply: Power outages in many communes. Specifically:

+ Power outage 148/178 lines.

+ Number of transformer stations with power outages in the whole Company: 6169/7963 transformer stations;

+ Number of customers with power outages in the whole Company: 868,313/1,095,811 customers;

2. Expected remedial process:

Units are checking, assessing and repairing damage.

3. Summary of damage caused by natural disasters up to 07:00 on August 26, 2025:

* For 110kV lines:

* For Medium Voltage lines:

- Number of broken, collapsed, or drifting columns: 32 (columns);

- Tilted, collapsed, cracked columns: 11 (columns);

* For Transformer Station:

- Number of damaged substations: 01 (substation);

- Number of damaged transformers: 01 (MBA).

* For Low Voltage Line:

- Number of low voltage power poles broken or fallen: 425 (poles);

- Number of low voltage power poles tilted and cracked: 68 (poles);

Source: https://baonghean.vn/lanh-dao-cong-ty-dien-luc-nghe-an-thong-tin-tien-do-cap-dien-tro-lai-10305245.html


Comment (0)

No data
No data

Same tag

Same category

Summary of A80 training: Vietnam's strength shines under the night of the thousand-year-old capital
Hanoi traffic chaos after heavy rain, drivers abandon cars on flooded roads
Impressive moments of the flight formation on duty at the A80 Ceremony
More than 30 military aircraft perform for the first time at Ba Dinh Square

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product