Field survey of progress of Ba Lai 8 bridge project on coastal road

On the afternoon of July 25, at Thanh Phuoc commune, Mr. Nguyen Truc Son - Member of the Provincial Party Standing Committee, Vice Chairman of the Provincial People's Committee came to survey the progress of the Ba Lai 8 bridge project on the coastal road of the province.

Báo Vĩnh LongBáo Vĩnh Long25/07/2025

On the afternoon of July 25, at Thanh Phuoc commune, Mr. Nguyen Truc Son - Member of the Provincial Party Standing Committee, Vice Chairman of the Provincial People's Committee came to survey the progress of the Ba Lai 8 bridge project on the coastal road of the province.

Mr. Nguyen Truc Son - Vice Chairman of the Provincial People's Committee chaired the meeting, listening to the progress report of the Ba Lai 8 bridge project on the coastal road.
Mr. Nguyen Truc Son - Vice Chairman of the Provincial People's Committee chaired the meeting, listening to the progress report of the Ba Lai 8 bridge project on the coastal road.

After the departments, branches and localities reported on the project progress, Vice Chairman of the Provincial People's Committee - Nguyen Truc Son said that the project is large-scale, with 4 bidding packages allocating capital of over 1,033 billion VND, but after 7 months of implementation, only more than 5.5% has been disbursed - very low compared to the target of 25% of the whole province. The reason is due to slow site clearance, lack of coordination between departments, branches and local authorities. Difficulties in supplying raw materials, especially sand and stone.

Accordingly, Vice Chairman of the Provincial People's Committee - Nguyen Truc Son requested departments, branches and local authorities to urgently complete site clearance work before the end of August 2025. Assign relevant departments and branches to coordinate to remove difficulties in sand supply; focus maximum resources, search for and ensure raw materials, proactively propose solutions, and coordinate to speed up progress.

Mr. Nguyen Truc Son - Vice Chairman of the Provincial People's Committee and the working group surveyed the construction site of Ba Lai 8 bridge.
Mr. Nguyen Truc Son - Vice Chairman of the Provincial People's Committee and the working delegation surveyed the construction site of Ba Lai 8 bridge.

Regarding disbursement progress, the Vice Chairman of the Provincial People's Committee requested to disburse a minimum of VND 100 billion/month, a maximum of VND 200 billion/month in the remaining 5 months of 2025. Authorities at all levels must coordinate closely, promote leadership and direction, concentrate resources, and ensure construction progress.

News and photos: THACH THAO

Source: https://baovinhlong.com.vn/thoi-su/202507/khao-sat-thuc-dia-tien-do-du-an-cau-ba-lai-8-tren-tuyen-duong-bo-ven-bien-dbf4084/


Comment (0)

No data
No data
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony
S-300PMU1 missiles on combat duty to protect Hanoi's sky
Lotus blooming season attracts tourists to the majestic mountains and rivers of Ninh Binh
Cu Lao Mai Nha: Where wildness, majesty and peace blend together
Hanoi is strange before storm Wipha makes landfall
Lost in the wild world at the bird garden in Ninh Binh
Pu Luong terraced fields in the pouring water season are breathtakingly beautiful
Asphalt carpets 'sprint' on North-South highway through Gia Lai
PIECES of HUE - Pieces of Hue
Magical scene on the 'upside down bowl' tea hill in Phu Tho

Heritage

Figure

Business

No videos available

News

Political System

Local

Product