Proactively handle difficulties and obstacles to implement projects on schedule

DNO - On the afternoon of August 20, Vice Chairwoman of the City People's Committee Nguyen Thi Anh Thi chaired a meeting to listen to relevant units report on the implementation of projects and difficulties and obstacles in Ngu Hanh Son ward.

Báo Đà NẵngBáo Đà Nẵng20/08/2025

1(4).jpg
Vice Chairwoman of the City People's Committee Nguyen Thi Anh Thi chaired the meeting. Photo: T. HUY

According to the report of the Danang City Land Fund Development Center - Branch Area 2 (Ngu Hanh Son), the total number of projects being implemented in 2025 is 16 projects.

Of which, Group I in 2024 has 6 projects with a total of 273 records requiring site clearance; Group I in 2025 has 2 projects with a total of 9 records requiring site clearance; Group II in 2025 has 8 projects with a total of 270 records requiring site clearance.

The total number of land handovers is currently 175. Up to now, 2 projects have been completed (the project to clear and upgrade Ba Bang Nhan Street - Dang Thai Than Street (group I/2025) and the project of the area adjacent to the west of FPT Technology Urban Area (APU area - Pacific University, group II/2025).

The capital plan from the 2025 budget is over 178 billion VND, the accumulated expenditure to date is 175 billion VND. The total number of arranged lots is 309 lots.

At the meeting, relevant units specifically reported on difficulties and problems in site clearance at 16 projects in the area, mainly related to compensation cost estimates, resettlement arrangements, lack of actual resettlement land, and people not complying with site handover.

Vice Chairwoman of the City People's Committee Nguyen Thi Anh Thi requested agencies, units and localities to organize meetings with people, mobilize people to hand over the land, and in case of non-compliance, organize enforcement according to regulations.

For other difficulties and problems, based on the functions, tasks and authority of each unit and locality, there will be specific solutions to handle and resolve them, ensuring that projects are implemented on schedule.

Source: https://baodanang.vn/chu-dong-xu-ly-kho-khan-vuong-mac-de-trien-khai-cac-du-an-dung-tien-do-3299895.html


Comment (0)

No data
No data
People joyfully welcome the 80th anniversary of National Day
Vietnam women's team beat Thailand to win bronze medal: Hai Yen, Huynh Nhu, Bich Thuy shine
People flock to Hanoi, immersing themselves in the heroic atmosphere before National Day.
Suggested locations to watch the parade on National Day September 2
Visit Nha Xa silk village
See beautiful photos taken by flycam by photographer Hoang Le Giang
When young people tell patriotic stories through fashion
More than 8,800 volunteers in the capital are ready to contribute to the A80 festival.
The moment the SU-30MK2 "cuts the wind", air gathers on the back of the wings like white clouds
'Vietnam - Proudly Stepping Forward to the Future' Spreads National Pride

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product