Close-up of Long Thanh airport fuel tank accelerating to the finish line

Long Thanh airport's fuel supply system includes tanks and underground pipes to the apron, allowing direct refueling of aircraft, modern and safe.

VTC NewsVTC News30/08/2025

Close-up of Long Thanh airport fuel tank accelerating to the finish line - 1

Package 4.9, construction of an aircraft fuel supply system at Long Thanh Airport with a total investment of more than VND2.8 trillion, is being accelerated.

Close-up of Long Thanh airport fuel tank accelerating to the finish line - 2

Package 4.9 started construction in October 2024, and was scheduled to be completed in June 2026 according to the contract. However, following the Prime Minister 's directive to shorten the schedule, the investor adjusted the plan, basically completing the construction part before December 19, 2025 to ensure synchronization with the entire project.

Close-up of Long Thanh airport fuel tank accelerating to the finish line - 3

The bid package for the construction of an aircraft fuel station at Long Thanh Airport has a capacity of 5,200 m³/day, including 6 fuel tanks, meeting the needs of synchronous exploitation.

Close-up of Long Thanh airport fuel tank accelerating to the finish line - 4

Six floating aircraft fuel tanks were built with a capacity of 6,000 m³ each, ensuring the ability to store and supply fuel on a large scale.

Close-up of Long Thanh airport fuel tank accelerating to the finish line - 5
Close-up of Long Thanh airport fuel tank accelerating to the finish line - 6

According to VTC News Electronic Newspaper reporters, at the construction site, the joint venture contractor mobilized nearly 700 personnel and more than 80 machines and equipment to implement the construction package.

Close-up of Long Thanh airport fuel tank accelerating to the finish line - 7

According to the adjusted schedule, the construction of 6 aircraft fuel tanks at Long Thanh Airport will be completed before December 5, 2025.

Close-up of Long Thanh airport fuel tank accelerating to the finish line - 8

The fuel pipeline system to the tanks at Long Thanh Airport has been basically completed, the pipe ends have been sealed and preserved to prevent dust and dirt from entering.

Close-up of Long Thanh airport fuel tank accelerating to the finish line - 9
Close-up of Long Thanh airport fuel tank accelerating to the finish line - 10

The fuel tank of more than 2.8 trillion is being accelerated.

Close-up of Long Thanh airport fuel tank accelerating to the finish line - 11

Meanwhile, the underground fuel pipeline system for aprons 1, 2, 3 and 4, located in front of the passenger terminal, is being installed. According to the plan, this work will be completed before October 20, 2025.

Source: https://vtcnews.vn/can-canh-bon-chua-nhien-lieu-san-bay-long-thanh-tang-toc-ve-dich-ar962546.html


Comment (0)

No data
No data

Same category

Su 30-MK2 fighter jets drop jamming shells, helicopters raise flags in the capital's sky
Feast your eyes on the Su-30MK2 fighter jet dropping a glowing heat trap in the sky of the capital
(Live) General rehearsal of the celebration, parade, and march to celebrate National Day September 2
Duong Hoang Yen sings a cappella "Fatherland in the Sunlight" causing strong emotions

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product