Decision approving the adjustment of the Ho Chi Minh Road Construction Investment Project, Eastern bypass of Buon Ma Thuot City

Việt NamViệt Nam29/11/2023

17:39, 11/28/2023

The Ministry of Transport (MOT) has just issued a decision approving the adjustment of the Ho Chi Minh Road Construction Investment Project, the eastern bypass of Buon Ma Thuot City (Project).

Accordingly, the Project implementation time will be adjusted from 2020, basically completed in 2024 and completed procedures for putting into operation in 2025. The total investment after adjustment is more than 1,841 billion VND.

The Ministry of Transport requests the Dak Lak Provincial Project Management Board to exercise the rights, obligations and responsibilities of the investor and the contents assigned and authorized according to Decision No. 729/QD-BGTVT dated June 15, 2023 of the Minister of Transport in organizing the implementation of the Project to ensure the progress and quality of the project; take full responsibility before the law and the Minister of Transport in the process of managing and implementing the Project, ensuring compliance with regulations on public investment, laws on construction and bidding for the Project.

Ho Chi Minh road project, eastern bypass of Buon Ma Thuot city.
Ho Chi Minh road project, eastern bypass of Buon Ma Thuot city.

Report to the Provincial People's Committee to direct relevant units to review the accuracy and reasonableness of compensation, support and resettlement costs; check the calculation methods, results and legality of specific land prices performed by the consulting unit; approve specific land prices to ensure compliance with land law regulations. Continue to inspect and review the order, procedures and implementation process of the Project, and deploy the next steps in compliance with current regulations. Strictly manage project cost items, ensuring that they do not exceed the total investment approved by the Ministry of Transport.

The Ho Chi Minh Road project, the eastern bypass of Buon Ma Thuot City, is over 39.6 km long, passing through the districts of Cu M'gar, Cu Kuin, Krong Pac and Buon Ma Thuot City.

Snow White


Source

Comment (0)

No data
No data
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony
S-300PMU1 missiles on combat duty to protect Hanoi's sky
Lotus blooming season attracts tourists to the majestic mountains and rivers of Ninh Binh
Cu Lao Mai Nha: Where wildness, majesty and peace blend together
Hanoi is strange before storm Wipha makes landfall
Lost in the wild world at the bird garden in Ninh Binh
Pu Luong terraced fields in the pouring water season are breathtakingly beautiful
Asphalt carpets 'sprint' on North-South highway through Gia Lai
PIECES of HUE - Pieces of Hue
Magical scene on the 'upside down bowl' tea hill in Phu Tho

Heritage

Figure

Business

No videos available

News

Political System

Local

Product