Vietnam.vn - Nền tảng quảng bá Việt Nam

Ha Tinh "finalizes" the first resettlement location for the North-South high-speed railway

(Baohatinh.vn) - Ha Tinh has selected the location to build the first resettlement area to serve the site clearance work for the high-speed railway project on the North-South axis.

Báo Hà TĩnhBáo Hà Tĩnh23/07/2025

bqbht_br_duong-sat-cao-toc1.jpg
The high-speed railway project on the North-South axis passes through Ha Huy Tap ward, 9.1 km long, with a land acquisition area of about 71 hectares.

Deputy Director of the Department of Construction Le Anh Son said: The Provincial People's Committee has agreed on the location and scale to organize the survey, complete the procedural documents and establish an investment project to build a resettlement area in Lien Vinh village, Ha Huy Tap ward (formerly Thach Dai commune, Ha Tinh city) to serve the construction of the high-speed railway project on the North-South axis.

The province also assigned the People's Committee of Ha Huy Tap ward and the Chairman of the People's Committee of the ward to decide on investment, organize the establishment, appraisal, approval and implementation of the project.

The People's Committee of Ha Huy Tap Ward is requested to urgently organize and implement the documents, procedures, establish a progress roadmap and related contents to invest in the construction of resettlement areas in accordance with the provisions of law, instructions on investment in the construction of resettlement areas of the Central Government and the Department of Construction.

The implementation process must be timely, in accordance with procedures and legal regulations, without causing loss or waste. The Chairman of the People's Committee of Ha Huy Tap Ward is fully responsible before the law, the Provincial People's Committee, the Chairman of the Provincial People's Committee and inspection, examination and auditing agencies for the content and implementation process of the project to ensure compliance with regulations; deploy on schedule to serve the project commencement on August 19, 2025 according to the Government 's plan.

bqbht_br_duong-sat-cao-toc.jpg
Localities in Ha Tinh have started site clearance work for the high-speed railway project on the North-South axis.

For the remaining resettlement areas, the province assigned the People's Committees of communes and wards to organize the establishment of detailed planning and master planning in accordance with regulations; complete the planning approval no later than August 15.

The Department of Construction, the Department of Finance and relevant units shall promptly provide guidance and remove difficulties and obstacles for localities in the process of implementing planning and building resettlement areas to serve the high-speed railway project on the North-South axis.

According to the plan, the goal is to start construction of the remaining resettlement areas simultaneously in October 2025 and basically complete them before June 2026. The early completion of the construction of the resettlement areas is a very important task to facilitate the handover of at least 80% of the project site before December 2026 and the handover of the entire site before December 2027, meeting the general progress requirements of the Government.

The high-speed railway project on the North-South axis passes through 18 communes and 5 wards of the province with a total length of about 103.42 km. On the section through Ha Tinh, there are 3 stations (2 passenger stations, 1 freight station).

According to the review by the localities, the entire route through Ha Tinh is expected to affect nearly 2,000 households, of which about 1,279 households will have to be resettled. The localities have proposed planning to build 35 resettlement areas with a total area of about 87.4 hectares, with an estimated cost of about 1,100 billion VND.

The Standing Committee of Ha Tinh Provincial Party Committee has established a Steering Committee for Project Site Clearance and Compensation, with Secretary of the Provincial Party Committee Nguyen Duy Lam as Head of the Committee, Chairman of the Provincial People's Committee Vo Trong Hai as Permanent Deputy Head of the Committee, and Vice Chairmen of the Provincial People's Committee as Deputy Heads of the Committee.

The Provincial People's Committee has assigned specific tasks to each relevant department, branch, unit, and locality to implement site clearance work, detailed plans for the construction of resettlement areas, striving to hand over at least 80% of the site clearance area to investors by December 2026.

Source: https://baohatinh.vn/ha-tinh-chot-vi-tri-tai-dinh-cu-dau-tien-duong-sat-toc-do-cao-bac-nam-post292351.html


Comment (0)

No data
No data
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony
S-300PMU1 missiles on combat duty to protect Hanoi's sky
Lotus blooming season attracts tourists to the majestic mountains and rivers of Ninh Binh
Cu Lao Mai Nha: Where wildness, majesty and peace blend together
Hanoi is strange before storm Wipha makes landfall
Lost in the wild world at the bird garden in Ninh Binh
Pu Luong terraced fields in the pouring water season are breathtakingly beautiful
Asphalt carpets 'sprint' on North-South highway through Gia Lai
PIECES of HUE - Pieces of Hue
Magical scene on the 'upside down bowl' tea hill in Phu Tho

Heritage

Figure

Business

No videos available

News

Political System

Local

Product