On August 30, Vietnam Airports Corporation (ACV, the investor) said that in the passenger terminal category - considered the "heart" of the project - the joint venture contractor has mobilized more than 6,000 workers, maintaining construction 24/7.
To date, the underground part and four reinforced concrete floors of the project have been basically completed, many areas have begun rough construction, flooring, and tiling. From above, the "lotus" shaped roof has been revealed.
In parallel, equipment systems serving terminal operations such as baggage handling (BHS), aircraft landing gear (VDGS), escalators, and pedestrian stairs (ES/MW) have been transferred to the construction site, and some items are being installed.
In other packages including internal port traffic, technical infrastructure, fuel system, regulating lake, power supply, cargo terminal... more than 3,200 workers are also arranged to work during the holidays. ACV said all items are required to be completed by the end of this year, according to the plan.
The investor also arranged adequate staff to monitor and supervise, ensuring the construction takes place safely and with quality.
The Long Thanh airport project is built on an area of 5,000 hectares, with a total investment of nearly 336,630 billion VND, and is a national key project. When all three phases are completed, the project will have a capacity to serve 100 million passengers and 5 million tons of cargo per year. Phase one alone is expected to be operational from 2026 with the capacity to serve 25 million passengers and 1.2 million tons of cargo per year.
PV (synthesis)Source: https://baohaiphong.vn/thi-cong-xuyen-le-o-san-bay-long-thanh-519171.html